Construction term · Glossary
Electrical Safety (Construction)
Verified vs OSHA sources · 2026-10-27
Subpart K of 29 CFR Part 1926 addresses electrical safety for employees involved in construction work. It is divided into installation safety requirements (1926.402 through 1926.408), safety-related work practices (1926.416 and 1926.417), safety-related maintenance and environmental considerations (1926.431 and 1926.432) and safety requirements for special equipment (1926.441), with definitions in 1926.449 (1926.400). OSHA's electrical standards are designed to protect employees exposed to dangers such as electric shock, electrocution, fires and explosions. Ground-fault protection is by ground fault circuit interrupters (GFCIs) or an assured equipment grounding conductor program (1926.404(b)(1)). The work practices cover contact with energized lines, above or below ground, passing through or near the jobsite (1926.400), protection of employees who could contact a power circuit (1926.416) and tagging of controls and de-energized circuits (1926.417). Crane and derrick operations near power lines follow Subpart CC (1926.1407 through 1926.1411), and excavation near underground utilities follows 1926.651(b).
Also known as: Subpart K, construction electrical safety
On this page
Electrical Safety (Construction) at a glance
- Ground-fault protection (1926.404(b)(1)(i)): the employer uses either GFCIs or an assured equipment grounding conductor program to protect employees on construction sites, in addition to any other equipment grounding conductor provisions.
- The GFCI option of (b)(1)(ii) is written for 120-volt, single-phase, 15- and 20-ampere receptacle outlets that are not part of the permanent wiring of the building or structure and are in use by employees. A narrow exception covers receptacles on a two-wire, single-phase portable or vehicle-mounted generator whose circuit conductors are insulated from the generator frame and all other grounded surfaces.
- OSHA's interpretation letters of May 15, 2002 and February 7, 2005 say that the ground-fault protection duty of (b)(1)(i) has no voltage limit: it reaches 240-volt circuits and other outlets above 120 volts, which can be protected by an assured equipment grounding conductor program or by a GFCI designed for that voltage (OSHA treats the use of such a GFCI as a de minimis departure from the 120-volt wording). The 2002 letter says a hard-wired 240-volt unit with no outlet is outside the duty.
- The assured equipment grounding conductor program of (b)(1)(iii) covers all cord sets, receptacles not part of the building or structure, and equipment connected by cord and plug that are available for use or used by employees. It has a written description at the jobsite, one or more designated competent persons, a visual inspection before each day's use, continuity and receptacle tests on the schedule of (b)(1)(iii)(E), and a test record.
- Work practices (1926.416(a)): no employer permits an employee to work so close to any part of an electric power circuit that the employee could contact it, unless the employee is protected against shock by de-energizing and grounding the circuit or by guarding it effectively by insulation or other means. Before work begins, the employer ascertains by inquiry, direct observation or instruments whether an energized circuit, exposed or concealed, is located so that the work may bring any person, tool or machine into contact with it, posts and maintains warning signs where one exists, and advises employees of the location of such lines, the hazards and the protective measures. Where the exact location of underground power lines is unknown, employees using jackhammers, bars or other hand tools that may contact a line are provided with insulated protective gloves.
- Tagging (1926.417, titled 'Lockout and tagging of circuits'): controls to be deactivated during work on energized or de-energized equipment or circuits are tagged; de-energized equipment or circuits are rendered inoperative and have tags attached at all points where they can be energized; the tags plainly identify the equipment or circuits being worked on. The text of 1926.417 names tags and does not mention locks.
- Subpart K sets no single clearance distance. Crane and derrick operations near power lines follow Subpart CC: 1926.1407 (assembly and disassembly) and 1926.1408 (equipment operations) for lines up to 350 kV, 1926.1409 for lines over 350 kV, 1926.1410 (closer than the Table A zone) and 1926.1411 (traveling under or near power lines with no load). Excavation near underground utilities follows 1926.651(b), which has the employer determine the estimated location of utility installations before opening an excavation.
- OSHA's electrical page lists the most frequent causes of electrical injuries: contact with power lines, lack of ground-fault protection, a path to ground that is missing or discontinuous, equipment not used in the manner prescribed, and improper use of extension and flexible cords.
In plain English
The construction rules for protecting workers from electric shock, electrocution, fires and explosions. They cover ground-fault protection and work near live circuits. Circuits being worked on are tagged, and cranes near power lines follow Subpart CC.
What the rule says
“The employer shall use either ground fault circuit interrupters as specified in paragraph (b)(1)(ii) of this section or an assured equipment grounding conductor program as specified in paragraph (b)(1)(iii) of this section to protect employees on construction sites.”
In context
A concept governed primarily by OSHA's construction standards, 29 CFR Part 1926: the rules that apply on jobsites rather than the general-industry 1910 set.
Where this is written in OSHA's rules
- 29 CFR 1926 Subpart KRead on eCFR / OSHA.gov
- 29 CFR 1926.404(b)(1)(i)Read on eCFR / OSHA.gov
Example
In this invented illustration, a contractor sets up a temporary power panel. The 120-volt, 15- and 20-ampere receptacle outlets in use by employees are protected with GFCIs, and a 240-volt outlet on the same panel is covered by an assured equipment grounding conductor program, since the duty to provide ground-fault protection has no voltage limit. The program has a designated competent person, a visual inspection of cord sets before each day's use, tests on the schedule of 1926.404(b)(1)(iii)(E) and a test record. Before the crew works near a feeder, the contractor ascertains whether an energized circuit is located where the work could bring a person, tool or machine into contact with it, and posts warning signs where one exists. When an electrician de-energizes a circuit for repair, the circuit is rendered inoperative and tagged at all points where it can be energized (1926.417).
Why it matters
OSHA describes electricity as a long-recognized serious workplace hazard and lists electrocutions among the serious hazards of construction work. Its electrical page names contact with power lines, lack of ground-fault protection, a missing or discontinuous path to ground, equipment not used as prescribed and improper use of extension and flexible cords as the most frequent causes of electrical injuries. Subpart K answers with ground-fault protection (1926.404(b)(1)), protection of employees who could contact a power circuit (1926.416) and tagging of circuits being worked on (1926.417).
GFCI program vs. assured equipment grounding
Subpart K gives employers a choice for ground-fault protection: GFCIs under (b)(1)(ii), or an assured equipment grounding conductor program under (b)(1)(iii). The GFCI option is written for 120-volt, single-phase, 15- and 20-ampere receptacle outlets that are not part of the permanent wiring and are in use by employees. The program covers all cord sets, receptacles not part of the building or structure, and equipment connected by cord and plug, with a written description, designated competent persons, inspections, tests and a test record. OSHA's letters say the duty to provide ground-fault protection has no voltage limit, so outlets above 120 volts are protected by the program or by a GFCI designed for that voltage. In its 2005 letter, quoting the rule's preamble, OSHA says an employer may choose between the two on the basis of cost, a local GFCI rule, or flexibility in coordinating compliance with the other employers on the site.
Key areas of construction electrical safety (Subpart K)
| Area | What Subpart K says |
|---|---|
| Ground-fault protection | GFCIs (120-volt, single-phase, 15- and 20-ampere outlets in use by employees and not part of the permanent wiring) or an assured equipment grounding conductor program; OSHA's letters of 2002 and 2005 say the duty has no voltage limit (1926.404(b)(1)) |
| Work near power circuits | Employees who could contact a power circuit are protected by de-energizing and grounding it or by guarding it effectively; the employer ascertains the location of energized circuits before work, posts warning signs and advises employees (1926.416(a)) |
| Tagging of circuits | Controls to be deactivated are tagged; de-energized equipment and circuits are rendered inoperative and tagged at all points where they can be energized (1926.417) |
| Cords and cables | Worn or frayed cords or cables are not used; extension cords are not fastened with staples, hung from nails or suspended by wire; working spaces and walkways are kept clear of cords (1926.416(e), (b)(2)) |
| Cranes near power lines | Subpart CC, 1926.1407 through 1926.1411, not Subpart K |
Electrical Safety (Construction): frequently asked questions
- What is Electrical Safety (Construction)?
- Subpart K of 29 CFR Part 1926 addresses electrical safety for employees involved in construction work. It is divided into installation safety requirements (1926.402 through 1926.408), safety-related work practices (1926.416 and 1926.417), safety-related maintenance and environmental considerations (1926.431 and 1926.432) and safety requirements for special equipment (1926.441), with definitions in 1926.449 (1926.400). OSHA's electrical standards are designed to protect employees exposed to dangers such as electric shock, electrocution, fires and explosions. Ground-fault protection is by ground fault circuit interrupters (GFCIs) or an assured equipment grounding conductor program (1926.404(b)(1)). The work practices cover contact with energized lines, above or below ground, passing through or near the jobsite (1926.400), protection of employees who could contact a power circuit (1926.416) and tagging of controls and de-energized circuits (1926.417). Crane and derrick operations near power lines follow Subpart CC (1926.1407 through 1926.1411), and excavation near underground utilities follows 1926.651(b).
- What does OSHA's Subpart K cover for electrical safety in construction?
- Subpart K is divided into installation safety requirements (1926.402 through 1926.408), safety-related work practices (1926.416 and 1926.417), safety-related maintenance and environmental considerations (1926.431 and 1926.432), safety requirements for special equipment (1926.441) and definitions (1926.449) (29 CFR 1926.400). Key provisions are ground-fault protection by GFCIs or an assured equipment grounding conductor program (1926.404(b)(1)), protection of employees who could contact a power circuit (1926.416(a)) and tagging of controls and de-energized circuits (1926.417). Crane and derrick work near power lines follows Subpart CC, and excavation near underground utilities follows 1926.651(b).
- Do I need GFCIs on a construction site?
- The employer uses either GFCIs or an assured equipment grounding conductor program to protect employees (1926.404(b)(1)(i)). The GFCI option applies to 120-volt, single-phase, 15- and 20-ampere receptacle outlets on construction sites that are not part of the permanent wiring of the building or structure and are in use by employees ((b)(1)(ii)). The duty to provide ground-fault protection has no voltage limit, so 240-volt outlets are protected too, by the program or by a GFCI designed for that voltage (OSHA interpretation letters of May 15, 2002 and February 7, 2005). A hard-wired 240-volt unit with no outlet is outside the duty (2002 letter).
- Does Subpart K call for locks on de-energized circuits?
- 1926.417 is titled 'Lockout and tagging of circuits', and its text calls for tags: controls to be deactivated are tagged, and de-energized equipment or circuits are rendered inoperative and tagged at all points where they can be energized. The text does not mention locks and does not say how the circuit is rendered inoperative. General industry's lockout/tagout standard, 1910.147, excludes construction (1910.147(a)(1)(ii)).
- Why is electrical safety so critical in construction?
- OSHA describes electricity as a long-recognized serious workplace hazard and lists electrocutions among the serious hazards of construction work. Its electrical page names contact with power lines, lack of ground-fault protection, a missing or discontinuous path to ground, equipment not used as prescribed and improper use of extension and flexible cords as the most frequent causes of electrical injuries.
Related terms
Free tools for this
Governing OSHA standards
More Construction terms
The part of Title 29 of the Code of Federal Regulations that contains OSHA's General Industry standards, the default rulebook for most American workplaces (manufacturing, warehousing, healthcare, etc.) that are not covered by the construction, maritime or agriculture standards. It includes core rules such as Hazard Communication (1910.1200) and the air contaminant limits (1910.1000). Construction work is covered by Part 1926, which 1910.12(a) adopts as standards for every employee engaged in construction work, and some requirements are the same in both parts: 1926.59 says the HazCom requirements for construction are identical to those of 1910.1200.
29 CFR 1926The part of Title 29 of the Code of Federal Regulations that contains OSHA's Construction standards, the “Safety and Health Regulations for Construction.” It applies to construction work, which 1910.12(b) defines as work for construction, alteration, and/or repair, including painting and decorating, with construction-specific rules for fall protection (Subpart M), scaffolds (Subpart L), excavations (Subpart P), electrical (Subpart K) and more. OSHA decides by the activity being performed and not only by the employer's general business. Some general-industry (1910) standards apply to construction because 1926 adopts them (HazCom through 1926.59) or because 1910 identifies them as applicable to construction; OSHA's Field Operations Manual says a hazard in construction work that no specific 1926 standard covers is not normally cited under 1910 unless that standard has been identified as applicable to construction.
Anchor PointThe secure attachment point a personal fall arrest system (PFAS) ties off to. Under 29 CFR 1926.502(d)(15), anchorages used for attachment of personal fall arrest equipment are independent of any anchorage being used to support or suspend platforms and capable of supporting 5,000 pounds or more pounds per employee attached, or are designed, installed and used as part of a complete personal fall arrest system that maintains a safety factor of two or more, under the supervision of a qualified person.
Atmospheric TestingMeasuring the air in a confined space with an instrument before and during entry, as part of the evaluation of a permit space (1926.1204(e)) or of the alternate procedures for a space whose only hazard is atmospheric and is controlled by forced air ventilation, which call for a calibrated direct-reading instrument (1926.1203(e)(2)(iii)). Testing is done in a set order: first oxygen, then combustible gases and vapors, then toxic gases and vapors (1926.1204(e)(3)). Whether an atmosphere is hazardous is defined in 1926.1202: flammable gas, vapor or mist in excess of 10 percent of its lower flammable limit; oxygen below 19.5 percent or above 23.5 percent; a substance above its dose or permissible exposure limit; or any other atmospheric condition that is immediately dangerous to life or health. Readings within those ranges are one condition of an entry and are not enough on their own: the classification of the space, the permit, isolation, ventilation, an attendant and rescue also apply.
BenchingA method of protecting employees from cave-ins by excavating the sides of an excavation to form one or a series of horizontal levels or steps, usually with vertical or near-vertical surfaces between levels (1926.650(b)). Benching is one of the sloping and benching systems whose slopes and configurations are selected under 1926.652(b), by one of four options: a slope not steeper than 1½H:1V (Option 1), Appendices A and B (Option 2), other tabulated data (Option 3), or a design approved by a registered professional engineer (Option 4). Appendix B to Subpart P lists benched configurations for Type A and Type B soil in excavations 20 feet or less in depth, and it lists no benched configuration for Type C soil.
Competent Person (Excavation)In OSHA's excavation standard (Subpart P), a competent person is one who is capable of identifying existing and predictable hazards in the surroundings, or working conditions which are unsanitary, hazardous, or dangerous to employees, and who has authorization to take prompt corrective measures to eliminate them (1926.650(b)). The competent person inspects excavations, the adjacent areas and protective systems before the start of work, as needed throughout the shift (not a continuous watch), and after every rainstorm or other hazard increasing occurrence, when employee exposure can be reasonably anticipated (1926.651(k)(1)). Exposed employees are removed from the hazardous area when the competent person finds evidence of a possible cave-in or another hazardous condition, until the necessary precautions have been taken (1926.651(k)(2)). When Appendix A to Subpart P applies, a competent person also classifies each soil and rock deposit as stable rock, Type A, Type B or Type C, based on a visual and a manual analysis.
Confined SpaceA space that is large enough and so configured that an employee can bodily enter it, has limited or restricted means for entry and exit, and is not designed for continuous employee occupancy (1926.1202). It is a permit space (also called a PRCS) if it has one or more of these characteristics: it contains or has a potential to contain a hazardous atmosphere; it contains a material that has the potential for engulfing an entrant; it has an internal configuration such that an entrant could be trapped or asphyxiated by inwardly converging walls or by a floor that slopes downward and tapers to a smaller cross-section; or it contains any other recognized serious safety or health hazard. A competent person identifies the confined spaces and the permit spaces before work begins (1926.1203(a)). An employer that decides to have employees enter a permit space has a written permit space program (1926.1203(d)), or uses the alternate procedures of 1926.1203(e) when their conditions are met, and a permit space can be reclassified as a non-permit confined space only when a competent person determines that the requirements of 1926.1203(g) are met.
Controlling EmployerUnder OSHA's Multi-Employer Citation Policy (CPL 02-00-124), a controlling employer is an employer who has general supervisory authority over the worksite, including the power to correct safety and health violations itself or to have others correct them. Control can be established by contract or, in the absence of explicit contractual provisions, by the exercise of control in practice. In the policy's examples the controlling employer is a general contractor or a construction manager, and an architect or engineer is one only if the breadth of its involvement is sufficient. The policy works in two steps: first the employer's role (creating, exposing, correcting or controlling), then whether its actions were sufficient for that role. A controlling employer has a duty to exercise reasonable care to prevent and detect violations on the site, and it can be cited for another employer's violation of an OSHA standard even when none of its own employees are exposed, but only when it did not meet that duty.
Sources & verification
- 29 CFR 1926 Subpart K (eCFR / OSHA.gov)
- 29 CFR 1926.404(b)(1)(i) (eCFR / OSHA.gov)
- OSHA: Electrical
- eCFR: 29 CFR 1926 Subpart K, Electrical
- OSHA: Interpretation letter of May 15, 2002, ground fault protection for 120-volt and 240-volt circuits
- OSHA: Interpretation letter of February 7, 2005, 1926.404(b)(1) and 208-volt branch circuits
Checked against the eCFR and OSHA.gov. Last reviewed 2026-10-27. This glossary is general information, not legal advice; OSHA State-Plan states (e.g. California, Michigan) may adopt stricter requirements.
A related free tool
The free LOTO Procedure Generator covers a task related to Electrical Safety (Construction). Read the rule above first, then use the tool for your own workplace.
Get the Binder in Order Before the Inspector Arrives. Are You Ready?
OSHA inspections come unannounced, apart from the few exceptions listed in 29 CFR 1903.6. Get the binder in order before the opening conference, not during it.
Serious Violation
$16,550
per violation (max)
HazComFast Pro
$199/mo
10 jobsites, unlimited chemicals, unlimited workers
New sign-ups are paused. The free tools below need no account, and customers can log in as usual.
Your account keeps working as usual. Cancel anytime.