Excavation & Trench Safety: slope it, shore it, or shield it
Cave-ins pose the greatest risk to workers in a trench, and OSHA notes that one cubic yard of soil can weigh as much as a car. That is why Subpart P starts from a protective system. At 5 feet or deeper an excavation needs one unless it is cut entirely in stable rock. Under 5 feet it is exempt only when a competent person has examined the ground and found no indication of a potential cave-in. This hub turns 29 CFR 1926 Subpart P into numbers you can use on site: the slope your soil allows and the duties that depend on your depth. It also covers the competent-person inspection, which comes before work starts, as needed through the shift and after every rainstorm or other hazard-increasing event.
Verified against osha.gov · October 18, 2026
At a glance
Protective system
Required in every excavation, except one made entirely in stable rock, or under 5 ft where a competent person finds no cave-in indication
1926.652(a)(1)Maximum slopes
Stable rock vertical; Type A 3/4:1 (53°); Type B 1:1 (45°); Type C 1½:1 (34°)
Subpart P App. B, Table B-1Deeper than 20 ft
Sloping and benching must be designed by a registered professional engineer
Subpart P App. BEgress
A ladder, stairway or ramp in any trench 4 ft or deeper, within 25 ft of lateral travel
1926.651(c)(2)Atmosphere
Tested before entry in excavations deeper than 4 ft where oxygen deficiency or a hazardous atmosphere exists or could reasonably be expected to exist
1926.651(g)(1)(i)Daily inspection
A competent person inspects the excavation, the adjacent areas and the protective systems before work starts, as needed through the shift and after every rainstorm or other hazard-increasing event, whenever employee exposure can reasonably be anticipated
1926.651(k)(1)Every figure is a 29 CFR 1926 Subpart P threshold, verified against osha.gov on October 18, 2026. OSHA runs a National Emphasis Program on trenching and excavation; we do not publish a fatality count here because OSHA’s trenching page does not.
What does OSHA allow for this excavation?
Pick the soil classification and the depth to see the maximum allowable slope, the cut-back per side, and the Subpart P duties that depend on that depth, each with its CFR paragraph. Conditions at the site bring other duties, listed under “What each depth triggers” below. It runs on the same engine as the full Trench Protective System Selector.
Classification is a competent-person call based on at least one visual and one manual analysis from Appendix A. A layered system takes the class of its weakest layer, and the competent person reclassifies when conditions change, for example after rain (Appendix A (c)(2), (c)(4) and (c)(5)).
Pick the soil class and depth to see the maximum allowable slope, the cut-back, and the Subpart P duties that depend on that depth, each with its CFR paragraph.
Four ways to protect a trench
Subpart P gives you options, not one answer. The competent person picks the system that fits the soil, the depth, and the space available.
Sloping
Cut the walls back to an angle no steeper than the maximum allowable slope for the soil, and gentler when the slope shows signs of distress or when stored material, equipment or traffic add load near the edge. It needs no hardware but takes space: Type C at 1½:1 turns a 3 ft trench bottom 8 ft deep into a 27 ft opening at the surface.
1926.652(b); App. B (c)(3)Benching
Step the walls instead of cutting one continuous slope. Appendix B gives bench dimensions for Type A and Type B soil and none for Type C, where it allows only a simple slope or a shielded or supported vertical lower portion. Any other design needs tabulated data or a registered professional engineer.
Subpart P App. B; 1926.652(b)Shoring
Support the walls with a timber, hydraulic or other shoring system. The design comes from Appendices A, C and D, from the manufacturer's tabulated data, from other tabulated data approved by a registered professional engineer, or from a design by one. The written data or design stays at the job site while the system is built.
1926.652(c)Shielding
A trench box does not stop the wall from failing. It protects the workers inside it if the wall does. Its design comes from the same four options as shoring; for a manufactured box that means the manufacturer's tabulated data and limits. No one is inside it while it is installed, removed or moved vertically, and employees need protection from cave-ins when they enter and leave the shielded area.
1926.652(c), (g)Soil classification decides everything
The slope, and often the system, follow from the classification a competent person makes with the visual and manual tests in Appendix A. Get this wrong and every number after it is wrong.
| Class | Max slope | Angle | What it is |
|---|---|---|---|
| Stable rock | Vertical | 90° | Natural solid mineral matter that can be excavated with vertical sides and stay intact while exposed. An excavation entirely in stable rock does not require a protective system. |
| Type A soil | 3/4:1 | 53° | Cohesive soil with an unconfined compressive strength of 1.5 tsf or greater. It is NOT Type A if the soil is fissured, subject to vibration from heavy traffic or pile driving, previously disturbed, or part of a layered system dipping into the excavation at 4H:1V or steeper. |
| Type B soil | 1:1 | 45° | Cohesive soil above 0.5 tsf and below 1.5 tsf; granular cohesionless soil such as angular gravel, silt, silt loam and sandy loam; previously disturbed soil that is not Type C; soil with Type A strength that is fissured or subject to vibration; and dry rock that is not stable. |
| Type C soil | 1½:1 | 34° | The least stable class: cohesive soil at 0.5 tsf or less; granular soil such as gravel, sand and loamy sand; submerged soil or soil from which water is freely seeping; submerged rock that is not stable; and layered material dipping into the excavation at 4H:1V or steeper. |
Slopes are Table B-1 (Subpart P Appendix B); classifications are Appendix A. A short-term option allows Type A excavations 12 ft or less, open 24 hours or less, at 1/2:1 (63°).
What each depth triggers
These steps follow from depth alone. Conditions at the site bring other duties, and the table after the steps lists them.
- 4 ft
Egress + atmosphere
A ladder, stairway, ramp or other safe means of egress in any trench 4 ft or deeper, within 25 ft of lateral travel (1926.651(c)(2)). Above 4 ft, the atmosphere is tested before entry wherever oxygen deficiency or a hazardous atmosphere exists or could reasonably be expected to exist (1926.651(g)(1)(i)).
- 5 ft
Protective system
Required at 5 ft or deeper unless the excavation is entirely in stable rock. Under 5 ft it is required unless a competent person has examined the ground and found no indication of a potential cave-in (1926.652(a)(1)).
- 20 ft
Engineer design
Above 20 ft, sloping and benching must be designed by a registered professional engineer (Subpart P Appendix B, Table B-1).
- Any depth
Daily inspection & 2 ft set-back
A competent person inspects before work starts, as needed through the shift and after every rainstorm or other hazard-increasing occurrence, whenever employee exposure can reasonably be anticipated (1926.651(k)(1)). Spoil, materials and equipment stay at least 2 ft from the edge, or behind retaining devices sufficient to keep them from falling or rolling in, or both (1926.651(j)(2)).
Conditions at the site bring other duties
The depth steps leave out everything that depends on what is around the dig. Check each condition against the site. The duties come from 29 CFR 1926.651 and 1926.652, and none of them is triggered by depth alone.
| Condition at the site | Duty | Paragraph |
|---|---|---|
| Utilities or other installations may be underground | Estimate where they are before the excavation is opened, ask the owners to locate them, find the exact location by safe means as the work approaches, and protect, support or remove them while the excavation is open. | 29 CFR 1926.651(b) |
| Water is in the excavation or is accumulating (rain, groundwater, runoff) | No one works in accumulated or accumulating water unless adequate precautions are taken, such as special support or shield systems, water removal or a harness and lifeline. Water-removal equipment is monitored by a competent person. | 29 CFR 1926.651(h) |
| Buildings, walls, sidewalks or pavement are near the excavation | Provide shoring, bracing or underpinning where their stability is endangered. Do not excavate below the base or footing of a foundation or retaining wall where that could hazard employees, unless a support system is provided, the excavation is in stable rock, or a registered professional engineer has approved it. Do not undermine sidewalks or pavement without support or other protection. | 29 CFR 1926.651(i) |
| Lifting or digging equipment handles loads, or trucks are loaded or unloaded beside the excavation | No one is permitted underneath loads handled by lifting or digging equipment. Employees stand away from a vehicle being loaded or unloaded. | 29 CFR 1926.651(e) |
| Mobile equipment works next to the edge and the operator cannot see it clearly | Use a warning system such as barricades, hand or mechanical signals, or stop logs. | 29 CFR 1926.651(f) |
| Employees are exposed to public vehicular traffic | Provide and wear warning vests or other garments marked with or made of reflectorized or high-visibility material. | 29 CFR 1926.651(d) |
| Oxygen deficiency or another hazardous atmosphere exists or may develop, at any depth | Take precautions against exposure (respiratory protection or ventilation), keep a flammable gas under 20 percent of its lower flammable limit, and test as often as needed when controls are used. Keep emergency rescue equipment readily available, and attended when in use. | 29 CFR 1926.651(g)(1)(ii) to (iv) and (g)(2) |
| Loose rock or soil could fall or roll from the face of the excavation | Scale the face, install protective barricades at intervals, or use other means that give equivalent protection. | 29 CFR 1926.651(j)(1) |
| Employees or equipment cross over the excavation | Provide walkways, with guardrails that comply with 1926.502(b) where the walkway is 6 feet or more above a lower level. | 29 CFR 1926.651(l) |
| Trees, poles, pipes or other surface encumbrances create a hazard | Remove or support them as necessary to safeguard employees. | 29 CFR 1926.651(a) |
| Spoil, equipment or traffic sit near the edge of a slope, or the slope shows signs of distress | The actual slope is gentler than the maximum allowable slope: at least 1/2H:1V gentler where there are signs of distress, and by an amount a competent person sets where surcharge loads are present. | 29 CFR 1926 Subpart P App. B (c)(3) |
| People work on the face of a sloped or benched excavation above other people | Not permitted unless the employees at the lower level are adequately protected from falling, rolling or sliding material or equipment. | 29 CFR 1926.652(f) |
| A shield or support system is installed, used, moved or removed | Materials free from damage, used as the manufacturer specifies, members connected, removal from the bottom up, no one inside a shield while it is installed, removed or moved vertically, and manufacturer's data at the jobsite while the system is built. | 29 CFR 1926.652(c)(2), (d), (e) and (g) |
Subpart P is a daily-inspection standard
Subpart P asks for a competent person’s inspection every day employees are exposed: before work starts, as needed through the shift, and after every rainstorm or other hazard-increasing occurrence (1926.651(k)(1)). When the inspection finds a hazard, exposed employees leave the hazardous area until the precautions are in place (1926.651(k)(2)). The paragraph does not prescribe a written inspection log. A dated note of who inspected, when, and what they found is how you show afterward that the inspection happened.
This is what HazComFast keeps together
The daily competent-person inspection, the atmospheric tests, the competent-person designation itself, and the JHA behind the dig — timestamped in one place and exportable on demand, instead of a notebook in a truck.
Key facts
- A protective system is required in every excavation except one made entirely in stable rock, or one less than 5 ft deep where examination of the ground by a competent person provides no indication of a potential cave-in (29 CFR 1926.652(a)(1)) — shallow is a judgment someone has to make and own, not an automatic exemption.
- Table B-1 caps the slope by soil type: stable rock vertical (90°), Type A 3/4:1 (53°), Type B 1:1 (45°), Type C 1½:1 (34°). A short-term option allows Type A excavations 12 ft or less, open 24 hours or less, at 1/2:1 (63°).
- Sloping or benching for any excavation deeper than 20 ft must be designed by a registered professional engineer — Table B-1 stops being a sufficient answer at that depth.
- A stairway, ladder, ramp or other safe means of egress is required in trench excavations 4 ft or deeper, positioned so no worker travels more than 25 ft laterally to reach it (29 CFR 1926.651(c)(2)) — which means moving the ladder as the trench advances.
- Spoil, materials and equipment stay at least 2 ft back from the edge, or behind retaining devices sufficient to keep them from falling or rolling in, or both (29 CFR 1926.651(j)(2)). The atmosphere is tested before entry in excavations deeper than 4 ft where oxygen deficiency or a hazardous atmosphere exists or could reasonably be expected to exist (1926.651(g)(1)(i)).
- A competent person inspects the excavation, the adjacent areas and the protective systems daily: before work starts, as needed through the shift and after every rainstorm or other hazard-increasing occurrence, whenever employee exposure can reasonably be anticipated (29 CFR 1926.651(k)(1)). OSHA's National Emphasis Program on Trenching and Excavation (CPL 02-00-161, effective October 1, 2018) stays in effect until it is canceled or superseded.
Tools, guides and the standards
Free tools
- Competent Person Designation Letter
The signed designation, basis of competency, and stop-work authority — before the daily inspections start.
- Trench Protective System Selector
Slope, cut-back, top width, and the main duties at your depth — with a cross-section diagram.
- Job Hazard Analysis Builder
Break the dig into steps, hazards and controls.
- Daily Pre-Task / STA Card
Brief the crew before the shift.
- Confined Space Entry Permit
For a vault or manhole on the job, not the trench: Subpart AA does not apply to work Subpart P covers (1926.1201(b)(1)).
- Weekly Site Inspection
The whole-site self-inspection around the dig.
In-depth guides
- Does OSHA certify competent persons? The 4 documents that prove a designation
- The trench geometry problem: OSHA's slope table, computed
- Trenching & excavation safety: the OSHA requirements
- Is a trench a confined space? Subpart AA vs 1910.146
- The OSHA inspection process: what to expect
- Equipment lifecycle & inspection tracking
Excavation safety FAQ
At what depth does OSHA require trench protection?
Five feet, with a nuance most people miss. 29 CFR 1926.652(a)(1) requires every employee in an excavation to be protected from cave-ins by an adequate protective system, except when the excavation is made entirely in stable rock, or is less than 5 feet deep and examination of the ground by a competent person provides no indication of a potential cave-in. So under 5 feet is not automatically exempt — the exemption depends on a competent person actually examining the ground and concluding there is no cave-in potential.
What are the maximum allowable slopes for each soil type?
From Table B-1 of Appendix B to Subpart P: stable rock may be cut vertical (90°); Type A soil is 3/4:1, or 53° from horizontal; Type B is 1:1, or 45°; and Type C is 1½:1, or 34°. There is also a short-term option: a Type A excavation 12 feet or less deep that will be open 24 hours or less may be sloped at 1/2:1 (63°). Any sloping or benching deeper than 20 feet must be designed by a registered professional engineer.
How do you classify trench soil?
A competent person classifies it using the visual and manual tests in Appendix A to Subpart P. Type A is cohesive soil with an unconfined compressive strength of 1.5 tsf or greater, but no soil is Type A if it is fissured, subject to vibration from heavy traffic or pile driving, previously disturbed, or part of a layered system dipping into the excavation at 4H:1V or steeper. Type B includes cohesive soil above 0.5 and below 1.5 tsf, granular cohesionless soil such as angular gravel, silt, silt loam and sandy loam, previously disturbed soil that is not Type C, Type A-strength soil that is fissured or subject to vibration, and dry rock that is not stable. Type C covers cohesive soil at 0.5 tsf or less, granular soil such as gravel, sand and loamy sand, submerged soil or soil from which water is freely seeping, and submerged rock that is not stable.
Does a trench box mean I can skip the slope?
Yes. Shielding is an alternative to sloping, not an addition to it. A trench shield does not prevent the wall from collapsing; it protects the workers inside it if the wall moves. Its design comes from one of the four options in 1926.652(c); for a manufactured box that means the manufacturer's tabulated data and limits, kept in writing at the job site while the system is built. Employees must be protected from cave-ins when they enter and leave the shielded area, and no one is allowed inside while the shield is installed, removed or moved vertically (1926.652(g)(1)).
Does a trench need a ladder every 25 feet?
Effectively, yes. 29 CFR 1926.651(c)(2) requires a stairway, ladder, ramp or other safe means of egress in trench excavations 4 feet or more deep, located so that no employee has to travel more than 25 feet laterally to reach it. In a long trench that means multiple access points, or moving the ladder forward as the excavation advances. The 25 feet is lateral travel for each employee, so measure from the farthest point where anyone works.
Who has to inspect an excavation, and how often?
A competent person, meaning someone capable of identifying existing and predictable hazards who is authorized to take prompt corrective measures (29 CFR 1926.32(f)), must inspect the excavation, the adjacent areas and the protective systems daily: before work starts, as needed through the shift, and again after every rainstorm or other hazard-increasing occurrence (1926.651(k)(1)). These inspections are required whenever employee exposure can reasonably be anticipated. If the competent person finds evidence of a possible cave-in, a protective-system failure, a hazardous atmosphere or another hazardous condition, exposed employees are removed from the hazardous area until the necessary precautions have been taken (1926.651(k)(2)).
Sources
- osha.gov/trenching-excavation
- osha.gov/laws-regs/regulations/standardnumber/1926/1926.651
- osha.gov/laws-regs/regulations/standardnumber/1926/1926.652
- osha.gov/laws-regs/regulations/standardnumber/1926/1926SubpartPAppA
- osha.gov/laws-regs/regulations/standardnumber/1926/1926SubpartPAppB
- osha.gov/sites/default/files/publications/OSHA2226.pdf
- osha.gov/enforcement/directives/cpl-02-00-161
Protective-system trigger (1926.652(a)(1)), Table B-1 slopes, egress (1926.651(c)(2)), atmospheric testing (1926.651(g)(1)(i)), spoil set-back (1926.651(j)(2)), daily inspection (1926.651(k)(1)) and the table of other duties (1926.651 and 1926.652) read against the eCFR and osha.gov on October 18, 2026. The weight of a cubic yard of soil is from OSHA publication 2226. Soil classification is a competent-person determination made with the tests in Appendix A. General guidance, not legal advice; OSHA-approved State Plans may impose additional requirements.
Get the Binder in Order Before the Inspector Arrives. Are You Ready?
OSHA inspections come unannounced, apart from the few exceptions listed in 29 CFR 1903.6. Get the binder in order before the opening conference, not during it.
Serious Violation
$16,550
per violation (max)
HazComFast Pro
$199/mo
10 jobsites, unlimited chemicals, unlimited workers
New sign-ups are paused. The free tools below need no account, and customers can log in as usual.
Your account keeps working as usual. Cancel anytime.