Skip to content

Approaching: Feb 1, 2027 — 300A Posting Begins. Get ready →

Construction (29 CFR 1926)

Power Line Safety (Up to 350 kV) – Equipment Operations

Verified vs OSHA sources · 2026-10-19

29 CFR 1926.1408

29 CFR 1926.1408 governs power-line safety for cranes operating near lines up to 350 kV: before work, the employer must determine whether any part of the equipment or load could get within 20 feet of a power line, and if so, either have the line deenergized and visibly grounded (Option 1), keep a 20-foot clearance (Option 2), or determine the line's voltage and keep the Table A minimum clearance distance (Option 3); Options 2 and 3 carry the encroachment measures of (b).

29 CFR 1926.1408 at a glance

What it requires
For lines up to 350 kV: assess the 20-foot zone, then Option 1 (deenergize and ground), Option 2 (20 feet) or Option 3 (Table A distance)
Who it covers
Construction employers operating cranes near power lines under Subpart CC
Clearance rule
Determine if any part could get within 20 ft of a line and control it (1926.1408(a)(2))
Options
De-energize and ground, maintain 20-ft clearance, or use Table A distances
Max penalty (2026)
$16,550 per serious violation; $165,514 per willful
Common confusion
20 feet is not a universal minimum: the assessment threshold does not erase the three options, and Table A has 10 feet up to 50 kV and 15 feet over 50 to 200 kV; the value that follows "to" is up to and includes that value

What 29 CFR 1926.1408 requires (plain English)

29 CFR 1926.1408 sets the power-line safety requirements for cranes and other covered equipment operating near power lines up to 350 kV. Before operations begin, the employer must identify the work zone and determine whether any part of the equipment, load line, or load, operated up to the equipment's maximum working radius, could get closer than 20 feet to a power line.

If it could, the employer must use one of three options: have the utility de-energize and visibly ground the line; maintain the 20-foot clearance; or determine the line's voltage and maintain the corresponding minimum clearance distance from Table A. The encroachment-prevention measures of (b) concern Options 2 and 3: a planning meeting, non-conductive tag lines if tag lines are used, an elevated warning line at the clearance distance, and at least one of five measures (proximity alarm, dedicated spotter, automatic warning device, range limiter, insulating link); if the operator cannot see the warning line, a dedicated spotter is needed in addition to one of the others (1926.1408(b)). Operations below a line are barred unless it is de-energized and visibly grounded, with four listed exceptions (1926.1408(d)), and operators and crew must be trained on staying in the cab, evacuation, step potential and the limits of protective devices ((g)).

1926.1408 is part of Subpart CC (scoped by 1926.1400) alongside operator certification (1926.1427), keeping clear of loads (1926.1425), and rigging. For lines over 350 kV, 1926.1409 replaces the references to 20 feet with 50 feet, up to 1,000 kV. 1926.1410 allows operations inside the Table A distances only on a demonstration and cumulative measures, not on the presence of a spotter alone. Assembly and disassembly near lines are in 1926.1407 and travel without a load is in 1926.1411. A dedicated spotter is one of the five measures of (b)(4); if the operator is unable to see the elevated warning line, a dedicated spotter is used in addition to one of the other measures ((b)(3)). The employer assumes that all power lines are energized unless the utility owner/operator confirms that the line has been and continues to be deenergized and visibly grounded at the worksite ((e)); lines are presumed to be uninsulated unless the utility owner/operator or a registered engineer who is a qualified person with respect to electrical power transmission and distribution confirms that a line is insulated ((g)(1)(iii)). Where Option 3 is used, the utility owner/operator provides the requested voltage information within two working days of the employer's request ((c)).

What the source requires, in summary

Determine if any part of the equipment, load line or load (including rigging and lifting accessories), if operated up to the equipment's maximum working radius in the work zone, could get closer than 20 feet to a power line.
29 CFR 1926.1408(a)(2)Summarized, not quoted.

Key facts about 29 CFR 1926.1408

  • For lines up to 350 kV, 20 feet is the distance of the assessment of (a)(2) and the clearance of Option 2; Option 3 uses the Table A distance for the line's voltage (1926.1408(a)(2)).
  • Before work, the employer must determine if any part could get within 20 feet of a line (1926.1408(a)(2)).
  • The three options are de-energize and ground, maintain 20-foot clearance, or use Table A approach distances.
  • Table A sets 10 ft up to 50 kV, 15 ft to 200 kV, 20 ft to 350 kV, then 25, 35 and 45 ft for higher bands; with a verified voltage under Option 3 the required distance can be less than 20 ft, with all (b) measures.
  • Under Options 2 and 3: a planning meeting, non-conductive tag lines, an elevated warning line at the clearance distance, and at least one of five measures (proximity alarm, dedicated spotter, automatic warning device, range limiter, insulating link); if the operator cannot see the warning line, a dedicated spotter is needed in addition to one of the others (1926.1408(b)).
  • For lines over 350 kV, 1926.1409 applies, with 50 feet to 1,000 kV; operations inside the Table A distances are covered by 1926.1410 on conditions; 1926.1407 covers assembly/disassembly near lines and 1926.1411 travel without a load.

Scope: who 29 CFR 1926.1408 applies to

Regulatory framework
Construction (29 CFR 1926)
Citation reference
29 CFR 1926.1408
Enforcement status
In force and enforced
Jurisdiction
Federal OSHA (29 State-Plan jurisdictions may be stricter)

State-Plan states (e.g. California, Washington, Michigan) operate OSHA-approved programs that must be at least as effective as federal OSHA and frequently impose higher penalties or additional requirements.

Key requirements of 29 CFR 1926.1408

#What the section requires or covers
1Before beginning equipment operations, identify the work zone and determine whether any part of the equipment, load line or load could get closer than 20 feet to a power line (1926.1408(a))
2If so, use one of three options: confirm the line is deenergized and visibly grounded; keep the equipment, load line and load at least 20 feet away; or keep the minimum approach distance in Table A for the line's voltage (1926.1408(a)(2))
3Under the 20-foot and Table A options, hold a planning meeting, use non-conductive tag lines, erect an elevated warning line or barricade at the required distance, and apply at least one of a proximity alarm, a dedicated spotter, a warning device, a range limiting device or an insulating link (1926.1408(b))
4A dedicated spotter is required, in addition to the other measure, if the operator cannot see the elevated warning line (1926.1408(b)(3))
5Do not place any part of the equipment, load line or load below a power line unless the line is deenergized and visibly grounded, except in the cases listed in 1926.1408(d)(2)
6For power lines over 350 kV, 1926.1409 applies

Summarized from the text of 29 CFR 1926.1408.

Common Crane Power Line Safety violations

Deficiencies OSHA cites under 29 CFR 1926.1408 include the ones below, in no particular order. Each serious item carries up to $16,550 (2026).

  • No power-line assessment of the work zone before operations (1926.1408(a)(1)).
  • Operating where any part could get within 20 feet of a line up to 350 kV without meeting Option 1, 2 or 3 (1926.1408(a)(2)).
  • No planning meeting, warning line, or (b)(4) measure near a line, or no dedicated spotter when the operator cannot see the warning line (1926.1408(b)).
  • Treating a line as deenergized without the utility owner/operator's confirmation that it has been and continues to be deenergized and visibly grounded at the worksite (1926.1408(e), (a)(2)(i)).
  • Not applying the Table A distance for the verified voltage (1926.1408, Table A); lines over 350 kV are under 1926.1409.
  • The operator and crew members assigned to the equipment not trained on the steps after electrical contact with a line, the presumptions about power lines and the limits of warning and grounding devices, or a dedicated spotter not trained for the task (1926.1408(g)).

20 feet starts the assessment; Table A sets the distance by voltage

1926.1408(a)(2) requires an assessment: the employer determines whether any part of the equipment or load, at the maximum working radius, could get within 20 feet of the line, and if so, meets Option 1, 2 or 3. The threshold of 20 feet for lines up to 350 kV starts the options; closer work requires the utility to de-energize and ground the line, or a verified voltage with the Table A minimum approach distance for it (10 ft up to 50 kV, 15 ft to 200 kV, 20 ft to 350 kV, with all the (b) measures). The spotter is one of the measures admitted under (b), with a special case when the warning line is not visible to the operator.

What OSHA inspectors look for

A compliance officer checks that a work-zone power-line assessment was done, that the equipment and load keep the clearance of the option chosen: 20 feet for Option 2, or the Table A distance for the line's voltage for Option 3, and that the required encroachment-prevention measures of 1926.1408(b) are in place (planning meeting, non-conductive tag lines if tag lines are used, warning line, and at least one of a proximity alarm, dedicated spotter, automatic warning device, range limiter or insulating link, plus a spotter when the operator cannot see the warning line), or that the line was de-energized and visibly grounded.

Example: how a violation is cited

Hypothetical case: a crane's boom is operated near an overhead distribution line with no assessment of the work zone. 1926.1408(a) has the employer determine whether any part of the equipment, load line or load could get closer than 20 feet to a power line. A serious violation carries a penalty of up to $16,550.

Illustrative example, not a specific OSHA case.

Crane Power Line Safety compliance checklist

Each item is a requirement of 29 CFR 1926.1408 that OSHA may verify during an inspection.

  • Identify all power lines in and around the work zone before crane operations begin.
  • Determine if any part of the equipment or load could get within 20 feet at the maximum working radius.
  • Choose an option: de-energize and ground the line, maintain 20-foot clearance, or use Table A distances by voltage.
  • Hold the planning meeting, erect an elevated warning line, and implement at least one (b)(4) measure; add a dedicated spotter whenever the operator cannot see the warning line. Keep equipment and load out from below the line unless it is de-energized and visibly grounded (1926.1408(b), (d)). Train the operator and each crew member assigned to the equipment on what to do after electrical contact (stay in the cab unless fire or another emergency forces an exit, the safest way to evacuate, step potential, crew keeping away from the equipment and load, safe clearance distances), on the presumption that a line is energized and uninsulated until the utility owner or a qualified registered engineer confirms otherwise, on the limits of insulating links, proximity alarms and range-control devices, and on grounding and its limits; train each dedicated spotter to do the job and to apply the section (1926.1408(g)).
  • If tag lines are used, use non-conductive tag lines (1926.1408(b)(2)); under Option 3, request the voltage from the utility owner/operator, who provides it within two working days ((c)).
  • Assume that all power lines are energized unless the utility owner/operator confirms that the line has been and continues to be deenergized and visibly grounded at the worksite (1926.1408(e)).

2026 penalties for 29 CFR 1926.1408

Maximums set by 29 CFR 1903.15(d). 2026 maximums unchanged from 2025 (no CPI adjustment; OMB M-26-11), so not an increase; the serious and repeat policy minimums were revised with FOM chapter 6 (OSHA memo of May 21, 2026). The 2025 OSHA penalty levels remain in effect for 2026; OSHA made no inflation adjustment for 2026. 29 CFR 1903.15 identifies January 15, 2025 as the effective reference for these amounts, while OSHA's public penalties page currently references penalties assessed after Jan. 15, 2026.

Violation typeMinimumMaximumWhen it applies
Serious$1,085$16,550Death or serious physical harm could result, and the employer knew or could have known (29 U.S.C. 666(k)).
Other-Than-Serious$0$16,550Relates to safety/health but unlikely to cause death or serious harm.
Willful$11,823$165,514Intentional, knowing, or voluntary disregard of the requirement.
Repeated$4,256$165,514A substantially similar violation cited within the last 5 years.
Failure to AbateNone$16,550/dayup to $16,550 per day; the total is normally capped at 30 times the daily amount (FOM Ch.6)

Serious violations reach $16,550 and willful or repeat violations $165,514.

Maximums and the willful minimum are set by 29 CFR 1903.15(d); the serious and repeated minimums are OSHA policy floors from its annual penalty adjustment memo. OSHA applies gravity-based and size, good-faith and history reductions (FOM CPL 02-00-164 Ch.6). Estimates only, not legal advice.

The business case for Crane Power Line Safety compliance

1926.1408(a)(2) has the employer determine if any part of the equipment, load line or load (including rigging and lifting accessories), if operated up to the equipment's maximum working radius in the work zone, could get closer than 20 feet to a power line; if so, the employer meets the requirements of Option 1, Option 2 or Option 3.

State plans and their penalty rules

States listed by the volume of their federal construction citations, not by this standard. Penalties and enforcement vary by state. State-Plan states may impose higher penalties and additional requirements beyond federal 29 CFR 1926.1408.

State pages for 29 CFR 1926.1408

Frequently asked questions about 29 CFR 1926.1408

How far must a crane stay from a power line?

For power lines up to 350 kV, 20 feet is the distance of the assessment and of Option 2, and Table A can set a smaller or equal distance by voltage under Option 3. Under 1926.1408, before operations the employer must determine whether any part of the equipment, load line, or load could get within 20 feet of a line at the maximum working radius, and if so must have the line de-energized and visibly grounded, keep the 20-foot clearance, or verify the voltage and maintain the Table A approach distance (10 ft up to 50 kV, 15 ft to 200 kV, 20 ft to 350 kV, and more for higher voltages).

What are the options if a crane must work near a power line?

1926.1408 gives three: have the utility de-energize and visibly ground the line; maintain the minimum clearance, 20 feet for lines up to 350 kV; or determine the line's voltage and maintain the corresponding Table A minimum approach distance. Under the second and third options the encroachment-prevention measures of 1926.1408(b) apply (planning meeting, warning line, and at least one of a proximity alarm, dedicated spotter, automatic warning device, range limiter or insulating link, with a spotter added if the operator cannot see the warning line).

What training does 1926.1408 require for power-line contact?

1926.1408(g) has each operator and crew member assigned to work with the equipment trained on the procedures to be followed in the event of electrical contact with a power line: the danger of electrocution from the operator simultaneously touching the equipment and the ground, the importance of remaining inside the cab except where there is an imminent danger of fire, explosion, or other emergency, the safest means of evacuating, the danger of the potentially energized zone around the equipment (step potential), the need for crew to avoid approaching or touching the equipment and the load, and safe clearance distance; also on the presumptions that lines are energized and uninsulated, the limitations of insulating links, proximity alarms and range control devices, and grounding and its limitations.

Can you assume a power line is de-energized?

No. Under 1926.1408(e), the employer must assume that all power lines are energized unless the utility owner/operator confirms that the power line has been and continues to be deenergized and visibly grounded at the worksite.

Regulatory history of 29 CFR 1926.1408

1926.1408 was established in OSHA's 2010 cranes and derricks in construction final rule (75 FR 47906), which created Subpart CC.

Related glossary terms

Key terms that appear in 29 CFR 1926.1408, each with a full plain-English explainer.

Get the Binder in Order Before the Inspector Arrives. Are You Ready?

OSHA inspections come unannounced, apart from the few exceptions listed in 29 CFR 1903.6. Get the binder in order before the opening conference, not during it.

Serious Violation

$16,550

per violation (max)

HazComFast Pro

$199/mo

10 jobsites, unlimited chemicals, unlimited workers

New sign-ups are paused. The free tools below need no account, and customers can log in as usual.

Your account keeps working as usual. Cancel anytime.