A method of protecting employees from cave-ins by excavating the sides of an excavation to form one or a series of horizontal levels or steps, usually with vertical or near-vertical surfaces between levels (1926.650(b)). Benching is one of the sloping and benching systems whose slopes and configurations are selected under 1926.652(b), by one of four options: a slope not steeper than 1½H:1V (Option 1), Appendices A and B (Option 2), other tabulated data (Option 3), or a design approved by a registered professional engineer (Option 4). Appendix B to Subpart P lists benched configurations for Type A and Type B soil in excavations 20 feet or less in depth, and it lists no benched configuration for Type C soil.

29 CFR 1926.650(b)

Also known as: benching system

Benching at a glance

  • Cuts the excavation walls into horizontal steps to resist cave-in.
  • Appendix B (Option 2 of 1926.652(b)): benched excavations 20 feet or less in depth have a maximum allowable slope of ¾:1 in Type A soil and 1:1 in Type B soil, with maximum bench dimensions shown in Figure B-1. No benched configuration is listed for Type C soil. Sloping or benching for excavations greater than 20 feet deep is designed by a registered professional engineer (Table B-1, note 3).
  • Appendix B is one route, not the only one: 1926.652(b) also allows a slope not steeper than 1½H:1V (Option 1), other tabulated data (Option 3), or a design approved by a registered professional engineer (Option 4).
  • Often combined with sloping in the same excavation, which Appendix B treats as compound slopes and configurations.
  • Soil and rock deposits are classified under Appendix A to Subpart P (Appendix B, paragraph (c)(1)), and the actual slope is cut back from the maximum allowable slope when there are signs of distress or surcharge loads.

In plain English

Digging the trench walls into stair-steps instead of a straight drop. Appendix B lists benched layouts for Type A and Type B soil but not Type C. The steps make a collapse of the sides less likely.

What the rule says

“Benching (Benching system) means a method of protecting employees from cave-ins by excavating the sides of an excavation to form one or a series of horizontal levels or steps, usually with vertical or near-vertical surfaces between levels.”
29 CFR 1926.650(b)

In context

A concept governed primarily by OSHA's construction standards, 29 CFR Part 1926: the rules that apply on jobsites rather than the general-industry 1910 set.

29 CFR 1926

Where this is written in OSHA's rules

Example

In this invented illustration, the soil in a 12-foot-deep excavation is classified as Type B under Appendix A. Appendix B allows a benched excavation of 20 feet or less in Type B soil with a maximum allowable slope of 1:1 and the maximum bench dimensions of Figure B-1. Whether a planned layout of benches qualifies depends on those bench dimensions, the overall slope, the depth, any signs of distress and any surcharge loads. A layout that Appendix B does not cover is designed under another option of 1926.652(b), for example by a registered professional engineer.

Why it matters

Using a benching layout in soil where Appendix B lists none, or with dimensions Appendix B does not give, leaves a cave-in hazard unaddressed: Appendix B has no benched configuration for Type C soil. The soil is classified first, and a misclassification changes which layouts are available.

Benching vs. sloping

Sloping cuts the walls back at a continuous angle; benching cuts them into horizontal steps. Under Appendix B, benched configurations are listed for Type A and Type B soil, and simple slopes are listed for every soil type (1½:1 for Type C), each for excavations 20 feet or less in depth and each subject to the other conditions of the appendix.

What Appendix B to Subpart P lists, by soil type

Soil typeBenched configuration in Appendix B?
Stable rockTable B-1 shows a vertical maximum allowable slope; an excavation made entirely in stable rock is an exception from protective systems (1926.652(a)(1)(i))
Type AYes: maximum allowable slope of ¾:1 with the maximum bench dimensions of Figure B-1
Type BYes: maximum allowable slope of 1:1 with the maximum bench dimensions of Figure B-1
Type CNo benched configuration is listed; a simple slope of 1½:1 is listed

Benching: frequently asked questions

What is Benching?
A method of protecting employees from cave-ins by excavating the sides of an excavation to form one or a series of horizontal levels or steps, usually with vertical or near-vertical surfaces between levels (1926.650(b)). Benching is one of the sloping and benching systems whose slopes and configurations are selected under 1926.652(b), by one of four options: a slope not steeper than 1½H:1V (Option 1), Appendices A and B (Option 2), other tabulated data (Option 3), or a design approved by a registered professional engineer (Option 4). Appendix B to Subpart P lists benched configurations for Type A and Type B soil in excavations 20 feet or less in depth, and it lists no benched configuration for Type C soil.
Can you bench Type C soil?
Appendix B lists no benched configuration for Type C soil. It lists a simple slope of 1½:1 and vertically sided lower portions that are shielded or supported. Type C soil is protected by an adequate protective system designed under 1926.652(b) or (c), such as sloping at 1½H:1V, shoring or a trench box or shield, unless an exception of 1926.652(a)(1) applies: an excavation made entirely in stable rock, or one less than 5 feet deep where a competent person's examination provides no indication of a potential cave-in.
What is the difference between benching and sloping?
Benching cuts the excavation walls into horizontal steps; sloping cuts them back at a continuous angle. Appendix B lists benched configurations only for Type A and Type B soil, and simple slopes for every soil type at the maximum allowable slope for that type.
Who decides if benching is acceptable?
The employer or its designee selects and constructs the slopes and configurations under one of the four options of 1926.652(b). Option 2 uses Appendices A and B, and the other options use a 1½H:1V slope, tabulated data or a design approved by a registered professional engineer.

Related terms

Free tools for this

Governing OSHA standards

More Construction terms

29 CFR 1910

The part of Title 29 of the Code of Federal Regulations that contains OSHA's General Industry standards, the default rulebook for most American workplaces (manufacturing, warehousing, healthcare, etc.) that are not covered by the construction, maritime or agriculture standards. It includes core rules such as Hazard Communication (1910.1200) and the air contaminant limits (1910.1000). Construction work is covered by Part 1926, which 1910.12(a) adopts as standards for every employee engaged in construction work, and some requirements are the same in both parts: 1926.59 says the HazCom requirements for construction are identical to those of 1910.1200.

29 CFR 1926

The part of Title 29 of the Code of Federal Regulations that contains OSHA's Construction standards, the “Safety and Health Regulations for Construction.” It applies to construction work, which 1910.12(b) defines as work for construction, alteration, and/or repair, including painting and decorating, with construction-specific rules for fall protection (Subpart M), scaffolds (Subpart L), excavations (Subpart P), electrical (Subpart K) and more. OSHA decides by the activity being performed and not only by the employer's general business. Some general-industry (1910) standards apply to construction because 1926 adopts them (HazCom through 1926.59) or because 1910 identifies them as applicable to construction; OSHA's Field Operations Manual says a hazard in construction work that no specific 1926 standard covers is not normally cited under 1910 unless that standard has been identified as applicable to construction.

Anchor Point

The secure attachment point a personal fall arrest system (PFAS) ties off to. Under 29 CFR 1926.502(d)(15), anchorages used for attachment of personal fall arrest equipment are independent of any anchorage being used to support or suspend platforms and capable of supporting 5,000 pounds or more pounds per employee attached, or are designed, installed and used as part of a complete personal fall arrest system that maintains a safety factor of two or more, under the supervision of a qualified person.

Atmospheric Testing

Measuring the air in a confined space with an instrument before and during entry, as part of the evaluation of a permit space (1926.1204(e)) or of the alternate procedures for a space whose only hazard is atmospheric and is controlled by forced air ventilation, which call for a calibrated direct-reading instrument (1926.1203(e)(2)(iii)). Testing is done in a set order: first oxygen, then combustible gases and vapors, then toxic gases and vapors (1926.1204(e)(3)). Whether an atmosphere is hazardous is defined in 1926.1202: flammable gas, vapor or mist in excess of 10 percent of its lower flammable limit; oxygen below 19.5 percent or above 23.5 percent; a substance above its dose or permissible exposure limit; or any other atmospheric condition that is immediately dangerous to life or health. Readings within those ranges are one condition of an entry and are not enough on their own: the classification of the space, the permit, isolation, ventilation, an attendant and rescue also apply.

Competent Person (Excavation)

In OSHA's excavation standard (Subpart P), a competent person is one who is capable of identifying existing and predictable hazards in the surroundings, or working conditions which are unsanitary, hazardous, or dangerous to employees, and who has authorization to take prompt corrective measures to eliminate them (1926.650(b)). The competent person inspects excavations, the adjacent areas and protective systems before the start of work, as needed throughout the shift (not a continuous watch), and after every rainstorm or other hazard increasing occurrence, when employee exposure can be reasonably anticipated (1926.651(k)(1)). Exposed employees are removed from the hazardous area when the competent person finds evidence of a possible cave-in or another hazardous condition, until the necessary precautions have been taken (1926.651(k)(2)). When Appendix A to Subpart P applies, a competent person also classifies each soil and rock deposit as stable rock, Type A, Type B or Type C, based on a visual and a manual analysis.

Confined Space

A space that is large enough and so configured that an employee can bodily enter it, has limited or restricted means for entry and exit, and is not designed for continuous employee occupancy (1926.1202). It is a permit space (also called a PRCS) if it has one or more of these characteristics: it contains or has a potential to contain a hazardous atmosphere; it contains a material that has the potential for engulfing an entrant; it has an internal configuration such that an entrant could be trapped or asphyxiated by inwardly converging walls or by a floor that slopes downward and tapers to a smaller cross-section; or it contains any other recognized serious safety or health hazard. A competent person identifies the confined spaces and the permit spaces before work begins (1926.1203(a)). An employer that decides to have employees enter a permit space has a written permit space program (1926.1203(d)), or uses the alternate procedures of 1926.1203(e) when their conditions are met, and a permit space can be reclassified as a non-permit confined space only when a competent person determines that the requirements of 1926.1203(g) are met.

Controlling Employer

Under OSHA's Multi-Employer Citation Policy (CPL 02-00-124), a controlling employer is an employer who has general supervisory authority over the worksite, including the power to correct safety and health violations itself or to have others correct them. Control can be established by contract or, in the absence of explicit contractual provisions, by the exercise of control in practice. In the policy's examples the controlling employer is a general contractor or a construction manager, and an architect or engineer is one only if the breadth of its involvement is sufficient. The policy works in two steps: first the employer's role (creating, exposing, correcting or controlling), then whether its actions were sufficient for that role. A controlling employer has a duty to exercise reasonable care to prevent and detect violations on the site, and it can be cited for another employer's violation of an OSHA standard even when none of its own employees are exposed, but only when it did not meet that duty.

Crane Operator Certification

Under 29 CFR 1926.1427, the employer ensures that each operator of equipment covered by Subpart CC is trained, certified or licensed, and evaluated before operating it (1926.1427(a)). Where a state or local government issues operator licenses under a program that meets 1926.1427(c)(1), the operator is licensed by that government for equipment within its jurisdiction. Otherwise the operator is certified by an accredited crane-operator testing organization (1926.1427(d)) or by an audited employer program (1926.1427(e)). A testing organization provides certification based on equipment type, or type and capacity (1926.1427(d)(1)(ii)(B)). An operator who is an employee of the U.S. military meets the section with a current military qualification for the equipment, which is not portable (1926.1427(a)(3)). Certification or a license is one part: the employer also trains the operator and evaluates the operator under 1926.1427(f), including the size and configuration of the equipment. The section excepts operators of derricks, sideboom cranes and equipment with a maximum manufacturer-rated hoisting/lifting capacity of 2,000 pounds or less, and the training provisions in their own sections continue to apply (1926.1427(a)(2)).

Sources & verification

Checked against the eCFR and OSHA.gov. Last reviewed 2026-10-27. This glossary is general information, not legal advice; OSHA State-Plan states (e.g. California, Michigan) may adopt stricter requirements.

A related free tool

The free Trench Protective System Selector covers a task related to Benching. Read the rule above first, then use the tool for your own workplace.

Get the Binder in Order Before the Inspector Arrives. Are You Ready?

OSHA inspections come unannounced, apart from the few exceptions listed in 29 CFR 1903.6. Get the binder in order before the opening conference, not during it.

Serious Violation

$16,550

per violation (max)

HazComFast Pro

$199/mo

10 jobsites, unlimited chemicals, unlimited workers

New sign-ups are paused. The free tools below need no account, and customers can log in as usual.

Your account keeps working as usual. Cancel anytime.