What 29 CFR 1910.269 requires (plain English)
29 CFR 1910.269 covers the operation and maintenance of electric power generation, control, transformation, transmission, and distribution lines and equipment: the work of electric utilities, and equivalent installations of industrial establishments ((a)(1)(i)(A)); the voltage alone does not decide the scope.
Its core protections include: de-energizing and grounding lines and equipment before work (and the conditions for energized work); minimum approach distances that workers and their conductive objects must keep from energized parts, scaled to the voltage; protection from electric arcs, which requires the employer to assess the incident heat energy of potential arcs and provide arc-rated protective clothing and equipment; rules for specific tasks (grounding, live-line tools, aerial devices, enclosed spaces, and more); and requirements for host and contract employers to share information and coordinate. Only qualified employees, trained and demonstrating the required skills, perform work on or near energized parts.
1910.269 (with its construction counterpart in 1926 Subpart V) is the specialized rule for utility electrical work, distinct from the general electrical standards (1910.331–.335) that cover most other workplaces. 1910.269(a)(1) also reaches fuel and ash handling, water and steam installations and chlorine and hydrogen systems at a generating station, test sites for temporary electrical testing, work directly associated with covered installations, and line-clearance tree trimming for utilities; it does not apply to construction work (except line-clearance tree trimming and the generation-installation work named in 1926.950(a)(3)) or to installations and work practices covered by Subpart S; and it applies in addition to the other Part 1910 standards ((a)(1)(ii)-(iii)).