What 29 CFR 1926.756 requires (plain English)
29 CFR 1926.756 governs the placement of beams and columns during steel erection: the sections are general (a), diagonal bracing (b), double connections at columns (c), column splices (d) and perimeter columns (e). It is part of Subpart R (Steel Erection).
Under (a)(1), during the final placing of solid web structural members, the load must not be released from the hoisting line until the member is secured with at least two bolts per connection, of the same size and strength as shown in the erection drawings, drawn up wrench-tight (or the equivalent as specified by the project structural engineer of record). Exceptions and additions: solid web structural members used as diagonal bracing may be secured with at least one bolt per connection ((b)); a competent person determines whether more than two bolts are needed for cantilevered members ((a)(2)); double connections at columns must keep at least one bolt connected to the first member unless a seat or equivalent device secures it ((c)); column splices resist a minimum eccentric gravity load of 300 pounds ((d)); and perimeter columns extend 48 inches above the finished floor and carry holes or devices at 42-45 inches and at the midpoint for perimeter safety cables, except where constructibility does not allow ((e)). The four-anchor-rod minimum for columns, and the competent person's evaluation of columns for guying or bracing, are in the separate column anchorage section, 1926.755(a)(1) and (a)(4).
Column anchorage is in 1926.755, not in 1926.756: all columns are anchored by a minimum of 4 anchor rods (anchor bolts) (1926.755(a)(1)); each column anchor rod assembly is designed to resist a minimum eccentric gravity load of 300 pounds located 18 inches from the extreme outer face of the column in each direction at the top of the column shaft ((a)(2)); and all columns are evaluated by a competent person to determine whether guying or bracing is needed ((a)(4)). The repair, replacement or field modification of anchor rods is not done without the approval of the project structural engineer of record (1926.755(b)(1)). 1926.756(c)(2) has a seat or equivalent device used for a double connection designed to support the load during the double connection process and adequately bolted or welded to both a supporting member and the first member before the nuts on the shared bolts are removed.