29 CFR 1926.1436 sets the supplemental requirements for derricks used in construction: powered equipment consisting of a mast or equivalent member held at or near the end by guys or braces, with or without a boom, and its hoisting mechanism, including A-frame, basket, breast, Chicago boom, gin pole (except gin poles used for erection of communication towers), guy, shearleg, and stiffleg derricks. All sections of Subpart CC apply to derricks unless the section specifies otherwise; derrick operators are trained under (q), and 1926.1427 (operator qualification and certification) does not apply.

29 CFR 1926.1436 at a glance

What it covers
Derricks in construction (A-frame, gin pole, guy, stiffleg, and more)
What a derrick is
Powered equipment with a mast or equivalent member held at or near the end by guys or braces, and its hoisting mechanism
Applies with
The general Subpart CC requirements, unless the section specifies otherwise
Main paragraphs
Load charts (b), construction (c), anchoring and guying (d), hoists (e), operational aids (f), tests (g), inspections (p), operator training (q)
Rule of 2010
Subpart CC replaced the former 1926.550 crane and derrick standard
Max penalty (2026)
$16,550 per serious violation; $165,514 per willful

What 29 CFR 1926.1436 requires (plain English)

29 CFR 1926.1436 sets the supplemental requirements for derricks in construction, within Subpart CC (Cranes and Derricks in Construction). A derrick is powered equipment consisting of a mast or equivalent member that is held at or near the end by guys or braces, with or without a boom, and its hoisting mechanism; the mast or equivalent member and/or the load is moved by the hoisting mechanism and operating ropes. Derricks include A-frame, basket, breast, Chicago boom, gin pole (except gin poles used for erection of communication towers), guy, shearleg, and stiffleg derricks.

This section contains supplemental requirements for derricks; all the other sections of Subpart CC apply to derricks unless specified otherwise. The section names its exceptions: 1926.1417 (Operation) applies except 1926.1417(c) ((b)(1)); 1926.1416 (Operational aids) applies except its boom hoist limiting device, boom angle or radius indicator and load weighing provisions ((f)(1)); 1926.1427 (operator qualification and certification) does not apply, and the employer trains each derrick operator on the safe operation of the equipment the individual will operate ((q)). New hoists are load tested to a minimum of 110% and not more than 125% of rated capacity, unless otherwise recommended by the manufacturer ((e)(2)(ii)); new or reinstalled derricks have their anchorages approved by a qualified person, a functional test with no hook load and a load test of at least 100% and no more than 110% of rated capacity by a competent person, documented ((g)); repaired or modified derricks are evaluated by a qualified person to determine if a load test is necessary ((h)). If power fails, the operator sets all brakes or locking devices and moves all clutch and other power controls to the off position ((j)). Derrick operations are supervised by a competent person ((o)), and inspections add the daily check of guys for proper tension and the annual checks of the gudgeon pin and foundation supports ((p)).

The 2010 cranes and derricks rule (Subpart CC) replaced the former 1926.550 standard and gave derricks these dedicated provisions. The section sets requirements by type: guy derricks have a minimum of 6 guys with equal spacing, unless a qualified person or the manufacturer approves variations and revises the rated capacity ((c)(2)(i)); stiffleg derricks have the mast supported by at least two stifflegs ((c)(3)(i)); gin pole guy lines are sized and spaced so as to make the gin pole stable in both boomed and vertical positions, or the derrick is not used in an unstable position ((c)(4)(i)).

What the source requires, in summary

This section contains supplemental requirements for derricks, whether temporarily or permanently mounted; all sections of this subpart apply to derricks unless specified otherwise.
29 CFR 1926.1436(a)Summarized, not quoted.

Key facts about 29 CFR 1926.1436

  • 1926.1436 sets supplemental requirements for derricks in construction (1926.1436(a)).
  • A derrick is powered equipment consisting of a mast or equivalent member held at or near the end by guys or braces, with or without a boom, and its hoisting mechanism (1926.1436(a)).
  • Types include A-frame, basket, breast, Chicago boom, gin pole (except gin poles used for erection of communication towers), guy, shearleg, and stiffleg (1926.1436(a)).
  • Operator duty: the employer must train each derrick operator on the safe operation of the equipment the individual will operate, and 1926.1427 (operator qualification and certification) does not apply (1926.1436(q)).
  • New or reinstalled derricks need, before initial use, anchorages approved by a qualified person (with special testing of rock or hairpin anchorages when the qualified person decides), a functional test with no hook load by a competent person, a load test by a competent person, and a document with the date, results and tester name kept until the next test or dismantling (1926.1436(g)(1)-(4)). Inspections add daily guy tension checks and annual gudgeon pin and foundation support checks ((p)).
  • The general Subpart CC crane rules also apply to derricks.
  • A signal person is required where 1926.1419 requires one; the qualification is in 1926.1428.
  • Subpart CC replaced the former 1926.550 crane and derrick standard in 2010.

Scope: who 29 CFR 1926.1436 applies to

Regulatory framework
Construction (29 CFR 1926)
Citation reference
29 CFR 1926.1436
Enforcement status
In force and enforced
Jurisdiction
Federal OSHA (29 State-Plan jurisdictions may be stricter)

State-Plan states (e.g. California, Washington, Michigan) operate OSHA-approved programs that must be at least as effective as federal OSHA and frequently impose higher penalties or additional requirements.

Key requirements of 29 CFR 1926.1436

#What the section requires or covers
1Apply the general Subpart CC crane rules plus these derrick-specific ones
2Erect, dismantle, and use derricks per manufacturer or qualified-engineer requirements
3Do not exceed the derrick's rated capacity
4Anchor and support the mast, guys, and braces properly
5Inspect derricks and use qualified operators and signal persons

Summarized from the text of 29 CFR 1926.1436.

Common Derricks violations

Deficiencies OSHA cites under 29 CFR 1926.1436 include the ones below, in no particular order. Each serious item carries up to $16,550 (2026).

  • Derrick not constructed to meet all stresses imposed on members and components when installed and operated in accordance with the manufacturer's or builder's procedures and within its rated capacity (1926.1436(c)(1)(i)).
  • Load anchoring data of the manufacturer or a qualified person not used, or mast base, guys or stifflegs not anchored as (d)(2)-(3) require (1926.1436(d)).
  • Load chart missing the contents of (b)(2), or not posted or readily available as (b)(3) requires (1926.1436(b)).
  • Not applying the general Subpart CC requirements to the derrick, except where the section specifies otherwise (1926.1436(a)).
  • Operator not trained on the safe operation of the derrick he or she runs (1926.1436(q)); the certification regime of 1926.1427 does not apply to derricks; no signal person where 1926.1419 requires one.
  • New or reinstalled derrick put into use without the qualified person's anchorage approval, the functional test, the load test or the test document (1926.1436(g)).

Subpart CC and the derrick-specific requirements

1926.1436(a) has supplemental requirements for derricks, whether temporarily or permanently mounted; all sections of Subpart CC apply to derricks unless specified otherwise. The general requirements (inspection, signal person, keeping clear of the load) apply with the derrick-specific ones. The operator of a derrick is trained under (q) and 1926.1427 does not apply; the training on the equipment remains required. New or reinstalled derricks have the tests and approvals of (g), and the inspections of (p) add the daily check of guy tension and annual checks.

What OSHA inspectors look for

A compliance officer checks that the load chart contains what (b)(2) lists, that load anchoring data developed by the manufacturer or a qualified person are used ((d)(1)), that new or reinstalled derricks were approved and tested under (g), that derrick operations are supervised by a competent person ((o)), and that the general Subpart CC requirements that apply to derricks are met. A signal person is required where 1926.1419 requires one: the point of operation is not in full view of the operator, the view in the direction of travel is obstructed when the equipment is traveling, or, due to site specific safety concerns, the operator or the person handling the load determines that it is necessary; the signal person qualification is in 1926.1428. A signal person is not required in every derrick operation.

Example: how a violation is cited

Hypothetical case: a new derrick is put into use without the anchorage approval of a qualified person, the functional test and the load test of 1926.1436(g). A serious violation carries a penalty of up to $16,550.

Illustrative example, not a specific OSHA case.

Derricks compliance checklist

Each item is a requirement of 29 CFR 1926.1436 that OSHA may verify during an inspection.

  • Keep a load chart with rated capacities by boom angle or radius, component lengths, reeving parts and rope size and construction, posted where visible for permanent installations or readily available at the job site otherwise (1926.1436(b)(2)-(3)).
  • Apply the general Subpart CC requirements (inspection, signal persons and the others that are not excluded), with derrick operators trained on the equipment they run under 1926.1436(q); 1926.1427 certification does not apply to derricks.
  • For a new or reinstalled derrick, before initial use: anchorage approved by a qualified person, functional test and load test by a competent person, and a test document with the date, results and tester name, retained until the derrick is re-tested or dismantled ((g)); then inspect under 1926.1412 plus the daily guy-tension check and the annual gudgeon pin and foundation support checks ((p)).
  • Have derrick operations supervised by a competent person ((o)) and keep employees clear of the load as 1926.1425 requires.

2026 penalties for 29 CFR 1926.1436

Maximums set by 29 CFR 1903.15(d). 2026 maximums unchanged from 2025 (no CPI adjustment; OMB M-26-11), so not an increase; the serious and repeat policy minimums were revised with FOM chapter 6 (OSHA memo of May 21, 2026). The 2025 OSHA penalty levels remain in effect for 2026; OSHA made no inflation adjustment for 2026. 29 CFR 1903.15 identifies January 15, 2025 as the effective reference for these amounts, while OSHA's public penalties page currently references penalties assessed after Jan. 15, 2026.

Violation typeMinimumMaximumWhen it applies
Serious$1,085$16,550Death or serious physical harm could result, and the employer knew or could have known (29 U.S.C. 666(k)).
Other-Than-Serious$0$16,550Relates to safety/health but unlikely to cause death or serious harm.
Willful$11,823$165,514Intentional, knowing, or voluntary disregard of the requirement.
Repeated$4,256$165,514A substantially similar violation cited within the last 5 years.
Failure to AbateNone$16,550/dayup to $16,550 per day; the total is normally capped at 30 times the daily amount (FOM Ch.6)

1926.1436 is part of Subpart CC. Serious violations reach $16,550 and willful or repeat violations $165,514.

Maximums and the willful minimum are set by 29 CFR 1903.15(d); the serious and repeated minimums are OSHA policy floors from its annual penalty adjustment memo. OSHA applies gravity-based and size, good-faith and history reductions (FOM CPL 02-00-164 Ch.6). Estimates only, not legal advice.

The business case for Derricks compliance

1926.1436(a) has supplemental requirements for derricks, whether temporarily or permanently mounted; all sections of Subpart CC apply to derricks unless specified otherwise. The section has requirements on tests, approvals, documents and inspections specific to derricks.

State plans and their penalty rules

States listed by the volume of their federal construction citations, not by this standard. Penalties and enforcement vary by state. State-Plan states may impose higher penalties and additional requirements beyond federal 29 CFR 1926.1436.

Frequently asked questions about 29 CFR 1926.1436

What is a derrick under OSHA 1926.1436?

A derrick is a lifting apparatus with a mast or equivalent member held at the top by guys or braces, with or without a boom, used with a hoisting mechanism to raise and lower loads. Under 1926.1436(a), the family includes A-frame, basket, breast, Chicago boom, gin pole (except gin poles used for erection of communication towers), guy, shearleg, and stiffleg derricks. The section sets supplemental Subpart CC requirements for them.

Do the general crane rules apply to derricks?

Yes. 1926.1436 contains supplemental requirements for derricks, and it states that all sections of Subpart CC apply to derricks unless specified otherwise. So a derrick must meet both the general Subpart CC requirements (inspection, operation, signal persons, keeping clear of the load; operators are trained under (q) and 1926.1427 certification does not apply) and the derrick-specific design, erection, and anchorage requirements.

What tests does a new or reinstalled derrick need?

1926.1436(g) has, for a new or reinstalled derrick before initial use, anchorages approved by a qualified person, a functional test by a competent person, a load test by a competent person, and a document with the date, results and tester name kept until the next test or dismantling.

What replaced the old 1926.550 cranes and derricks standard?

OSHA's Cranes and Derricks in Construction standard, Subpart CC (1926.1400 to 1926.1442), effective November 8, 2010, replaced the former 1926.550. Derricks specifically are addressed in 1926.1436, which supplements the general Subpart CC crane requirements with derrick-specific design, erection, anchorage, and use provisions.

Regulatory history of 29 CFR 1926.1436

Derricks were given dedicated provisions in 1926.1436 when OSHA issued the Cranes and Derricks in Construction standard (Subpart CC), effective November 8, 2010 (75 FR 47906), which replaced the former 1926.550. The section supplements the general Subpart CC requirements with the rules specific to derricks.

Related glossary terms

Key terms that appear in 29 CFR 1926.1436, each with a full plain-English explainer.

Get the Binder in Order Before the Inspector Arrives. Are You Ready?

OSHA inspections come unannounced, apart from the few exceptions listed in 29 CFR 1903.6. Get the binder in order before the opening conference, not during it.

Serious Violation

$16,550

per violation (max)

HazComFast Pro

$199/mo

10 jobsites, unlimited chemicals, unlimited workers

New sign-ups are paused. The free tools below need no account, and customers can log in as usual.

Your account keeps working as usual. Cancel anytime.