Skip to content

Approaching: Feb 1, 2027 — 300A Posting Begins. Get ready →

Construction (29 CFR 1926)

Hoisting Personnel

Verified vs OSHA sources · 2026-10-19

29 CFR 1926.1431

29 CFR 1926.1431 governs hoisting employees with a crane. It is prohibited except where the employer demonstrates that conventional means of reaching the work area (a personnel hoist, ladder, stairway, aerial lift, elevating work platform, or scaffold) would be more hazardous or are not possible because of the project's design or worksite conditions. The justification test does not apply to steel erection under Subpart R or to routine personnel access to an underground worksite by shaft under 1926.800 (1926.1431(a)). A personnel platform meeting (e) is required, except for the operations of (b)(2) (drill shafts up to 8 feet in diameter, pile driving, marine transfers, storage-tank, shaft and chimney operations), which follow (o), (p), (r) and (s); the platform is designed by a qualified person familiar with structural design ((e)(1)), and a custom-made platform is not excluded by itself.

29 CFR 1926.1431 at a glance

Default
Hoisting personnel with a crane is prohibited
The exception
Allowed only when conventional access is more hazardous or not possible
The platform
Designed by a qualified person familiar with structural design, supporting its own weight and at least five times the maximum intended load (e); not required for the operations of (b)(2)
Before the lift
Pre-lift meeting (m), trial lift and inspection (h), proof test at 125 percent (j)
During
Total load at or below 50 percent of rated capacity (d), controlled load lowering (d)(5)(vi), fall arrest except over water (k)(10)
Max penalty (2026)
$16,550 per serious violation; $165,514 per willful

What 29 CFR 1926.1431 requires (plain English)

29 CFR 1926.1431 sets the conditions for hoisting employees with equipment covered by Subpart CC; its requirements are supplemental to the other requirements of the subpart. The use of equipment to hoist employees is prohibited except where the employer demonstrates that the erection, use, and dismantling of conventional means of reaching the work area (such as a personnel hoist, ladder, stairway, aerial lift, elevating work platform, or scaffold) would be more hazardous, or is not possible because of the project's structural design or worksite conditions.

When personnel hoisting is justified, the workers ride in a personnel platform designed by a qualified person familiar with structural design, which remains within 10 degrees of level and supports, without failure, its own weight and at least five times the maximum intended load ((e)); hooks between the hoist line and the platform can be closed and locked ((g)). The equipment is uniformly level, within one percent of level grade, on footing a qualified person has determined to be sufficiently firm and stable, with all outriggers or stabilizers extended and locked to the same extension ((c)); it has the devices of (d)(5) that apply to it, such as a boom angle indicator and a boom hoist limiting device on a variable angle boom, an anti two-block device and a controlled load lowering system. A pre-lift meeting, attended by the operator, the signal person if used, the employees to be hoisted and the person responsible for the task, is held prior to the trial lift at each new work location and repeated for any employees newly assigned ((m)). The trial lift with the unoccupied platform loaded at least to the anticipated liftweight is performed immediately prior to each shift and repeated when the equipment is moved or the lift route changes ((h)(2)); the competent person checks that the required safety devices and operational aids are functioning and that the lift will not exceed 50 percent of rated capacity ((h)(3)); the proof test at 125 percent of the platform's rated capacity, held for five minutes, is made at each jobsite and after any repair or modification ((j)).

During the lift, hoisting is performed in a slow, controlled, cautious manner ((k)(1)); where the platform has no controls, the equipment operator remains at the equipment controls, on site and in view of the equipment, at all times while the platform is occupied ((k)(6)); occupants keep all parts of the body inside the platform, except when necessary to position the platform or while performing the duties of a signal person ((k)(2)(i)); except over water, where 1926.106 applies, occupants use a personal fall arrest system attached to a structural member within the platform ((k)(10)). The total load, including the hook, load line and rigging, does not exceed 50 percent of the rated capacity for the radius and configuration, except during proof testing ((d)). When wind speed exceeds 20 mph at the platform, a qualified person determines whether it is not safe to lift personnel, and if it is not, the lift does not begin or is terminated ((k)(8)); hoisting personnel within 20 feet of a power line up to 350 kV, or within 50 feet of one over 350 kV, is prohibited, except for work covered by Subpart V ((n)). The test of (a) is that conventional means would be more hazardous or are not possible.

The regulatory text

“The use of equipment to hoist employees is prohibited except where the employer demonstrates that the erection, use, and dismantling of conventional means of reaching the work area, such as a personnel hoist, ladder, stairway, aerial lift, elevating work platform, or scaffold, would be more hazardous, or is not possible because of the project's structural design or worksite conditions.”
29 CFR 1926.1431(a)

Key facts about 29 CFR 1926.1431

  • Hoisting employees with a crane is prohibited except as a last resort (1926.1431(a)); the test does not apply to Subpart R steel erection or routine shaft access under 1926.800. A platform is required (b)(1) except in a few listed operations such as drill shafts up to 8 feet in diameter, pile driving, marine transfers and storage-tank, shaft and chimney work (b)(2).
  • It is allowed only when conventional access would be more hazardous or is not possible (1926.1431(a)).
  • The personnel platform is designed by a qualified person familiar with structural design and supports, without failure, its own weight and at least five times the maximum intended load (1926.1431(e)(1), (e)(4)).
  • Free fall of the load line hoist is prohibited when hoisting personnel, and a controlled load lowering system is used ((d)(5)(vi), 1926.1426(d)).
  • The trial lift is performed immediately prior to each shift and repeated after a move or a change of lift route ((h)(2)); the proof test at 125 percent of the platform's rated capacity, held for five minutes, is made at each jobsite and after any repair or modification ((j)).
  • The pre-lift meeting is attended by the operator, the signal person if used, the employees to be hoisted and the person responsible for the task, prior to the trial lift at each new work location ((m)).
  • Hoisting is slow, controlled and cautious ((k)(1)), and the total load does not exceed 50 percent of the rated capacity for the radius and configuration, except during proof testing ((d)).

Scope: who 29 CFR 1926.1431 applies to

Regulatory framework
Construction (29 CFR 1926)
Citation reference
29 CFR 1926.1431
Enforcement status
In force and enforced
Jurisdiction
Federal OSHA (29 State-Plan jurisdictions may be stricter)

State-Plan states (e.g. California, Washington, Michigan) operate OSHA-approved programs that must be at least as effective as federal OSHA and frequently impose higher penalties or additional requirements.

Key requirements of 29 CFR 1926.1431

#What the section requires or covers
1Only when no less hazardous means available
2Use a personnel platform meeting specific criteria
3Trial lift and proof test required
4Limit load to 50% of rated capacity
5Provide personal fall arrest for each worker
6Maintain continuous visual or voice communication

Summarized from the text of 29 CFR 1926.1431.

Common Personnel Hoisting violations

Deficiencies OSHA cites under 29 CFR 1926.1431 include the ones below, in no particular order. Each serious item carries up to $16,550 (2026).

  • Hoisting personnel without demonstrating conventional access was more hazardous or impossible (1926.1431(a)).
  • Using a platform that does not meet the criteria of 1926.1431(e) where a personnel platform is required ((b)(1)).
  • No trial lift and inspection (1926.1431(h)), no proof test to 125 percent of the platform's rated capacity at each jobsite and after any repair or modification (1926.1431(j)), or improper rigging (1926.1431(g)).
  • No pre-lift meeting before the trial lift at each new location, with the operator, signal person, occupants and supervisor, repeated for new workers (1926.1431(m)).
  • Load line free fall during personnel hoisting, or no controlled load lowering system used (1926.1431(d)(5)(vi), 1926.1426(d)); operator not at the equipment controls while the platform is occupied ((k)(6)-(7)).

Justification and conditions of personnel hoisting

1926.1431(a) prohibits hoisting personnel except where the employer demonstrates that conventional means of reaching the work area (a personnel hoist, ladder, stairway, aerial lift, elevating work platform, or scaffold) would be more hazardous, or are not possible because of the project's structural design or worksite conditions. The test does not apply to steel erection under Subpart R or to routine personnel access to an underground worksite by shaft under 1926.800. A platform meeting the design criteria is required, except in the cases of (b)(2); the conformity of the design counts, not its commercial origin.

What OSHA inspectors look for

A compliance officer first asks whether personnel hoisting was justified at all, whether conventional access really was more hazardous or impossible, and then checks the platform design, the pre-lift meeting, the trial lift and proof test, and the controls (controlled load lowering, operator at the controls). The trial lift and the proof test are different checks: the trial lift is performed immediately prior to each shift in which personnel will be hoisted, and repeated when the equipment is moved to a new or previously used location or the lift route changes ((h)(2)); the proof test is at 125 percent of the platform's rated capacity, at each jobsite and after any repair or modification, with the platform held suspended for a minimum of five minutes ((j)).

Example: how a violation is cited

Hypothetical case: a crew hoists workers with a crane without the employer having demonstrated that conventional means of reaching the work area would be more hazardous or are not possible. 1926.1431(a) prohibits the use of equipment to hoist employees except under that demonstration. A serious violation carries a penalty of up to $16,550.

Illustrative example, not a specific OSHA case.

Personnel Hoisting compliance checklist

Each item is a requirement of 29 CFR 1926.1431 that OSHA may verify during an inspection.

  • Demonstrate that conventional access would be more hazardous or is not possible before hoisting personnel (1926.1431(a)).
  • Use a personnel platform meeting (e), designed by a qualified person familiar with structural design, except for the operations of (b)(2).
  • Set up the equipment uniformly level, within one percent of level grade, on footing a qualified person has determined to be sufficiently firm and stable, with all outriggers or stabilizers extended and locked (1926.1431(c)).
  • Make the trial lift with the unoccupied platform loaded at least to the anticipated liftweight immediately prior to each shift, and again when the equipment is moved or the lift route changes (1926.1431(h)(2)); proof test the platform and rigging to 125 percent of rated capacity at each jobsite and after repair or modification (1926.1431(j)).
  • Hold a pre-lift meeting with the operator, the signal person if used, the employees to be hoisted and the person responsible for the task, prior to the trial lift at each new work location, and repeat it for employees newly assigned (1926.1431(m)).
  • Use controlled load lowering, not free fall (1926.1431(d)(5)(vi)), and keep the equipment operator at the equipment controls, on site and in view of the equipment, while the platform is occupied ((k)(6)-(7)).
  • Employees on the platform use a personal fall arrest system attached to a structural member within the platform (except over water, where 1926.106 applies), and keep their body parts inside (1926.1431(k)(10)).
  • No hoisting personnel within 20 feet of a power line up to 350 kV or within 50 feet of one over 350 kV, except Subpart V work (1926.1431(n)); when wind at the platform exceeds 20 mph a qualified person decides whether to lift or must stop the lift (k)(8); keep the total load at or below 50 percent of the rated capacity for the radius and configuration (d)(1)-(3), except during proof testing.

2026 penalties for 29 CFR 1926.1431

Maximums set by 29 CFR 1903.15(d). 2026 maximums unchanged from 2025 (no CPI adjustment; OMB M-26-11), so not an increase; the serious and repeat policy minimums were revised with FOM chapter 6 (OSHA memo of May 21, 2026). The 2025 OSHA penalty levels remain in effect for 2026; OSHA made no inflation adjustment for 2026. 29 CFR 1903.15 identifies January 15, 2025 as the effective reference for these amounts, while OSHA's public penalties page currently references penalties assessed after Jan. 15, 2026.

Violation typeMinimumMaximumWhen it applies
Serious$1,085$16,550Death or serious physical harm could result, and the employer knew or could have known (29 U.S.C. 666(k)).
Other-Than-Serious$0$16,550Relates to safety/health but unlikely to cause death or serious harm.
Willful$11,823$165,514Intentional, knowing, or voluntary disregard of the requirement.
Repeated$4,256$165,514A substantially similar violation cited within the last 5 years.
Failure to AbateNone$16,550/dayup to $16,550 per day; the total is normally capped at 30 times the daily amount (FOM Ch.6)

Serious violations reach $16,550 and willful or repeat violations $165,514.

Maximums and the willful minimum are set by 29 CFR 1903.15(d); the serious and repeated minimums are OSHA policy floors from its annual penalty adjustment memo. OSHA applies gravity-based and size, good-faith and history reductions (FOM CPL 02-00-164 Ch.6). Estimates only, not legal advice.

The business case for Personnel Hoisting compliance

1926.1431(a) has the use of equipment to hoist employees prohibited except where the employer demonstrates that the erection, use, and dismantling of conventional means of reaching the work area would be more hazardous, or is not possible because of the project's structural design or worksite conditions; the section sets the platform, the tests, the meeting and the controls that apply when the hoisting is allowed.

State plans and their penalty rules

States listed by the volume of their federal construction citations, not by this standard. Penalties and enforcement vary by state. State-Plan states may impose higher penalties and additional requirements beyond federal 29 CFR 1926.1431.

State pages for 29 CFR 1926.1431

Frequently asked questions about 29 CFR 1926.1431

Can you lift workers with a crane?

Only as a last resort. Under 1926.1431, hoisting employees with a crane is prohibited unless the employer demonstrates that conventional means of reaching the work area (a personnel hoist, ladder, stairway, aerial lift, elevating work platform, or scaffold) would be more hazardous or are not possible because of the project's design or worksite conditions. When justified, it requires a personnel platform meeting 1926.1431(e), except in the operations of (b)(2), and the set-up, tests, meeting and work practices of the section.

What is required before hoisting personnel with a crane?

Under 1926.1431, the employer demonstrates that conventional access is more hazardous or not possible ((a)), uses a personnel platform meeting (e), sets up the equipment as (c) requires, holds the pre-lift meeting of (m) with the operator, the signal person if used, the employees to be hoisted and the person responsible for the task, performs the trial lift and inspection of (h), and the proof test of (j) at each jobsite. Free fall of the load line is prohibited and controlled load lowering is used ((d)(5)(vi)).

Is a custom-made personnel platform allowed?

Where a platform is required, it must meet 1926.1431(e): designed by a qualified person familiar with structural design, with a connection that keeps it within 10 degrees of level, a suspension system designed to minimize tipping, and the capacity to support, without failure, its own weight and at least five times the maximum intended load. The conformity of the design matters, not whether the platform is custom-made.

Why is hoisting personnel restricted?

1926.1431(a) prohibits it except where the employer demonstrates that conventional means would be more hazardous or are not possible; when it is allowed, the platform, the trial lift, the proof test, the pre-lift meeting and the operating controls of the section apply.

Regulatory history of 29 CFR 1926.1431

The personnel-hoisting requirements in 1926.1431 are part of Subpart CC (75 FR 47906, effective November 8, 2010); the former 1926.550(g) is a historical text, not a current rule.

Related glossary terms

Key terms that appear in 29 CFR 1926.1431, each with a full plain-English explainer.

Get the Binder in Order Before the Inspector Arrives. Are You Ready?

OSHA inspections come unannounced, apart from the few exceptions listed in 29 CFR 1903.6. Get the binder in order before the opening conference, not during it.

Serious Violation

$16,550

per violation (max)

HazComFast Pro

$199/mo

10 jobsites, unlimited chemicals, unlimited workers

New sign-ups are paused. The free tools below need no account, and customers can log in as usual.

Your account keeps working as usual. Cancel anytime.