Skip to content

Approaching: Feb 1, 2027 — 300A Posting Begins. Get ready →

Construction (29 CFR 1926)

Site Layout, Site-Specific Erection Plan, and Construction Sequence

Verified vs OSHA sources · 2026-10-19

29 CFR 1926.752

29 CFR 1926.752 governs site layout and the start of steel erection (Subpart R). Before steel erection begins, the controlling contractor must give the steel erector written notification that the concrete in the footings, piers, and walls (and the mortar in masonry piers and walls) has attained 75 percent of its intended minimum compressive design strength or sufficient strength to support the loads imposed during steel erection, the controlling contractor must also give written notification that any repairs, replacements and modifications to the anchor bolts were conducted in accordance with 1926.755(b) ((a)(2)), and the controlling contractor ensures that adequate access roads into and through the site and a firm, properly graded, drained area, readily accessible to the work, are provided and maintained ((c)). A steel erection contractor does not erect steel unless it has received the written notification on the concrete ((b)).

29 CFR 1926.752 at a glance

Concrete strength
75% of intended minimum compressive design strength, or sufficient strength for the loads imposed during erection, shown by an appropriate ASTM field-cured test and notified in writing before erection (1926.752(a)(1))
Who confirms it
The controlling contractor, in written notification to the steel erector
Site layout
Adequate access roads into and through the site, means and methods for pedestrian and vehicular control, and a firm, properly graded, drained area with adequate space for storage and equipment, provided and maintained by the controlling contractor ((c))
Erection plan
Site-specific erection plan only where the employer elects alternate means and methods ((e)); all hoisting pre-planned ((d))
Part of
Subpart R: Steel Erection (2001)
Max penalty (2026)
$16,550 per serious violation; $165,514 per willful

What 29 CFR 1926.752 requires (plain English)

29 CFR 1926.752 covers site layout and the conditions that must be met before steel erection can start, as part of Subpart R (Steel Erection).

The paragraphs are the approval to begin steel erection (a), the commencement of steel erection (b), the site layout (c), the pre-planning of overhead hoisting operations (d) and the site-specific erection plan (e). Before authorizing the commencement of steel erection, the controlling contractor must ensure that the steel erector is provided with written notification that the concrete in the footings, piers, and walls (and the mortar in masonry piers and walls) has attained, based on an appropriate ASTM field-cured test, either 75 percent of the intended minimum compressive design strength or sufficient strength to support the loads imposed during steel erection. A second written notification is required that any repairs, replacements and modifications to the anchor bolts were conducted in accordance with 1926.755(b), which requires the approval of the project structural engineer of record ((a)(2); 1926.755(b)(1)-(2)). 1926.752(b) has a steel erection contractor not erect steel unless it has received the written notification on the concrete. The controlling contractor ensures that the following is provided and maintained ((c)): adequate access roads into and through the site for the safe delivery and movement of derricks, cranes, trucks, other necessary equipment, and the material to be erected, and means and methods for pedestrian and vehicular control, with an exception for roads outside of the construction site; and a firm, properly graded, drained area, readily accessible to the work, with adequate space for the safe storage of materials and the safe operation of the erector's equipment; all hoisting operations in steel erection must be pre-planned to meet 1926.753(d) ((d)); and a site-specific erection plan, developed by a qualified person and available at the work site, is required where employers elect, due to conditions specific to the site, to develop alternate means and methods that provide employee protection in accordance with 1926.753(c)(5), 1926.757(a)(4) or 1926.757(e)(4) ((e)); guidelines for establishing the plan are in appendix A to the subpart.

The title of the section is Site layout, site-specific erection plan and construction sequence.

What the source requires, in summary

The concrete in the footings, piers and walls and the mortar in the masonry piers and walls has attained, on the basis of an appropriate ASTM standard test method of field-cured samples, either 75 percent of the intended minimum compressive design strength or sufficient strength to support the loads imposed during steel erection.
29 CFR 1926.752(a)(1)Summarized, not quoted.

Key facts about 29 CFR 1926.752

  • Before authorizing the commencement of steel erection, the controlling contractor ensures that the steel erector is provided with written notification on the strength of the concrete in the footings, piers and walls and of the mortar in the masonry piers and walls (1926.752(a)(1)).
  • The notification covers either 75% of the intended minimum compressive design strength or sufficient strength to support the loads imposed during steel erection.
  • The notification is written and goes to the steel erector.
  • A second written notification covers any repair, replacement or modification of the anchor bolts, conducted in accordance with 1926.755(b), which requires the approval of the project structural engineer of record (1926.752(a)(2)); before a column is erected the controlling contractor notifies the erector of any change to that column's anchor rods (1926.755(b)(2)).
  • It is based on an ASTM field-cured test method.
  • The controlling contractor ensures that adequate access roads into and through the site, means and methods for pedestrian and vehicular control, and a firm, properly graded, drained area readily accessible to the work are provided and maintained (1926.752(c)).
  • It is part of Subpart R (Steel Erection), issued in 2001.
  • A steel erection contractor does not erect steel unless it has received the written notification on the concrete (1926.752(b)).

Scope: who 29 CFR 1926.752 applies to

Regulatory framework
Construction (29 CFR 1926)
Citation reference
29 CFR 1926.752
Enforcement status
In force and enforced
Jurisdiction
Federal OSHA (29 State-Plan jurisdictions may be stricter)

State-Plan states (e.g. California, Washington, Michigan) operate OSHA-approved programs that must be at least as effective as federal OSHA and frequently impose higher penalties or additional requirements.

Key requirements of 29 CFR 1926.752

#What the section requires or covers
1Provide adequate access roads
2Verify anchor bolt placement
3Develop site-specific erection plan when required
4Sequence erection to maintain structural stability

Summarized from the text of 29 CFR 1926.752.

Common Steel Erection Site Layout violations

Deficiencies OSHA cites under 29 CFR 1926.752 include the ones below, in no particular order. Each serious item carries up to $16,550 (2026).

  • Starting steel erection without the required written concrete-strength notification (1926.752(a)(1)).
  • Erecting after an anchor bolt repair, replacement or modification without the written notification and the structural engineer's approval (1926.752(a)(2); 1926.755(b)).
  • A steel erection contractor erecting steel without having received the written notification on the concrete (1926.752(b)).
  • Access roads, pedestrian and vehicular control, or the firm, properly graded, drained area not provided and maintained (1926.752(c)).
  • No qualified-person site-specific erection plan available at the work site where the employer elected alternate means and methods in place of 1926.753(c)(5), 1926.757(a)(4) or 1926.757(e)(4) (1926.752(e)); hoisting operations not pre-planned to meet 1926.753(d) (1926.752(d)).
  • Controlling contractor not fulfilling its pre-erection duties (1926.752(a)).

Two duties on the written notification, and the two alternatives for the concrete

1926.752(a) is the duty of the controlling contractor: before authorizing the commencement of steel erection, it ensures that the steel erector is provided with the written notifications; (b) is the prohibition on the steel erection contractor, which does not erect steel unless it has received the written notification on the concrete. The notification on the concrete covers either 75 percent of the intended minimum compressive design strength or sufficient strength to support the loads imposed during steel erection, on the basis of an appropriate ASTM standard test method of field-cured samples, for the concrete in the footings, piers and walls and the mortar in the masonry piers and walls. A second written notification, (a)(2), covers any repairs, replacements and modifications to the anchor bolts conducted in accordance with 1926.755(b). A percentage of strength does not by itself guarantee the capacity of a foundation.

What OSHA inspectors look for

A compliance officer checks the points of 1926.752: the written notifications the controlling contractor ensures the steel erector is provided with before authorizing the commencement of steel erection (a)(1)-(2); the receipt of the notification on the concrete by the steel erection contractor before it erects steel (b); the access roads, the pedestrian and vehicular control, and the firm, properly graded, drained area (c); the pre-planning of hoisting operations (d); and the site-specific erection plan where (e) applies.

Example: how a violation is cited

Hypothetical case: a steel erection contractor erects columns without having received the written notification that the concrete in the footings, piers and walls has attained, on the basis of an appropriate ASTM standard test method of field-cured samples, either 75 percent of the intended minimum compressive design strength or sufficient strength to support the loads imposed during steel erection. 1926.752(b) has the steel erection contractor not erect steel without it, and (a)(1) has the controlling contractor ensure that the steel erector is provided with it. A serious violation carries a penalty of up to $16,550.

Illustrative example, not a specific OSHA case.

Steel Erection Site Layout compliance checklist

Each item is a requirement of 29 CFR 1926.752 that OSHA may verify during an inspection.

  • Have the controlling contractor ensure that the steel erector receives written notification, based on an appropriate ASTM standard test method of field-cured samples, that the concrete in the footings, piers and walls and the mortar in the masonry piers and walls reached 75% of the intended minimum compressive design strength or sufficient strength to support the loads imposed during steel erection, before erection is authorized (1926.752(a)(1)).
  • A steel erection contractor does not erect steel until it has received the written notification on the concrete (1926.752(b)).
  • Pass the anchor bolt notification too: any repair, replacement or modification of the anchor bolts, done in accordance with 1926.755(b) with the structural engineer of record's approval, goes to the erector in writing before erection is authorized ((a)(2)).
  • Provide and maintain adequate access roads into and through the site, with means and methods for pedestrian and vehicular control; roads outside of the construction site are excepted (1926.752(c)(1)).
  • Provide and maintain a firm, properly graded, drained area, readily accessible to the work, with adequate space for the safe storage of materials and the safe operation of the erector's equipment (1926.752(c)(2)).
  • Pre-plan every hoisting operation so that 1926.753(d) is met ((d)); prepare a qualified-person site-specific erection plan only where you elect alternate means and methods in place of 1926.753(c)(5), 1926.757(a)(4) or 1926.757(e)(4) ((e)), and keep it at the work site.

2026 penalties for 29 CFR 1926.752

Maximums set by 29 CFR 1903.15(d). 2026 maximums unchanged from 2025 (no CPI adjustment; OMB M-26-11), so not an increase; the serious and repeat policy minimums were revised with FOM chapter 6 (OSHA memo of May 21, 2026). The 2025 OSHA penalty levels remain in effect for 2026; OSHA made no inflation adjustment for 2026. 29 CFR 1903.15 identifies January 15, 2025 as the effective reference for these amounts, while OSHA's public penalties page currently references penalties assessed after Jan. 15, 2026.

Violation typeMinimumMaximumWhen it applies
Serious$1,085$16,550Death or serious physical harm could result, and the employer knew or could have known (29 U.S.C. 666(k)).
Other-Than-Serious$0$16,550Relates to safety/health but unlikely to cause death or serious harm.
Willful$11,823$165,514Intentional, knowing, or voluntary disregard of the requirement.
Repeated$4,256$165,514A substantially similar violation cited within the last 5 years.
Failure to AbateNone$16,550/dayup to $16,550 per day; the total is normally capped at 30 times the daily amount (FOM Ch.6)

Serious violations reach $16,550 and willful or repeat violations $165,514.

Maximums and the willful minimum are set by 29 CFR 1903.15(d); the serious and repeated minimums are OSHA policy floors from its annual penalty adjustment memo. OSHA applies gravity-based and size, good-faith and history reductions (FOM CPL 02-00-164 Ch.6). Estimates only, not legal advice.

The business case for Steel Erection Site Layout compliance

1926.752(a) has the controlling contractor, before authorizing the commencement of steel erection, ensure that the steel erector is provided with two written notifications: that the concrete in the footings, piers and walls and the mortar in the masonry piers and walls has attained, on the basis of an appropriate ASTM standard test method of field-cured samples, either 75 percent of the intended minimum compressive design strength or sufficient strength to support the loads imposed during steel erection; and that any repairs, replacements and modifications to the anchor bolts were conducted in accordance with 1926.755(b).

State plans and their penalty rules

States listed by the volume of their federal construction citations, not by this standard. Penalties and enforcement vary by state. State-Plan states may impose higher penalties and additional requirements beyond federal 29 CFR 1926.752.

State pages for 29 CFR 1926.752

Frequently asked questions about 29 CFR 1926.752

What must happen before steel erection can begin?

Under 1926.752, before authorizing steel erection the controlling contractor must ensure the steel erector is provided with written notification that the concrete in footings, piers, and walls and the mortar in masonry piers and walls has attained 75 percent of the intended minimum compressive design strength or sufficient strength to support the loads imposed during steel erection, based on an appropriate ASTM standard test method of field-cured samples. The controlling contractor also ensures the access roads and the firm, properly graded, drained area of (c), and the erector is notified in writing of any anchor bolt repair, replacement or modification ((a)(2)).

What does the notification on the concrete cover?

1926.752(a)(1) has the notification cover either 75 percent of the intended minimum compressive design strength or sufficient strength to support the loads imposed during steel erection, on the basis of an appropriate ASTM standard test method of field-cured samples.

Who is responsible for the concrete-strength notification?

The controlling contractor. Under 1926.752, the controlling contractor must ensure the steel erector receives the written concrete-strength notification before erection begins. The steel erection contractor does not erect steel unless it has received the notification (1926.752(b)).

What is a site-specific erection plan?

1926.752(e) has a site-specific erection plan developed by a qualified person and available at the work site, when an employer elects, due to conditions specific to the site, alternate means and methods in place of 1926.753(c)(5), 1926.757(a)(4) or 1926.757(e)(4); it is not required for every project. Separately, 1926.752(d) requires all steel-erection hoisting operations to be pre-planned to meet 1926.753(d). Guidelines for establishing the plan are in appendix A to the subpart.

Regulatory history of 29 CFR 1926.752

1926.752 is in Subpart R, published on January 18, 2001 (66 FR 5196) after a negotiated rulemaking; the notice of July 17, 2001 set the effective date at January 18, 2002.

Related glossary terms

Key terms that appear in 29 CFR 1926.752, each with a full plain-English explainer.

Get the Binder in Order Before the Inspector Arrives. Are You Ready?

OSHA inspections come unannounced, apart from the few exceptions listed in 29 CFR 1903.6. Get the binder in order before the opening conference, not during it.

Serious Violation

$16,550

per violation (max)

HazComFast Pro

$199/mo

10 jobsites, unlimited chemicals, unlimited workers

New sign-ups are paused. The free tools below need no account, and customers can log in as usual.

Your account keeps working as usual. Cancel anytime.