Barricades (Construction) — removed 2019, now 1926.200(g)

29 CFR 1926.202 (removed July 15, 2019)

29 CFR 1926.202 no longer exists as a standalone section. OSHA removed it, together with 1926.203, in the Standards Improvement Project-Phase IV final rule (84 FR 21416, May 14, 2019, effective July 15, 2019) because it duplicated the revised 1926.200(g). Today the rule that governs construction barricades is 29 CFR 1926.200(g): at points of hazard, construction areas must be posted with legible traffic control signs and protected by traffic control devices (g)(1), and the design and use of all traffic control devices (signs, signals, markings, barricades and other devices) for the protection of construction workers must conform to Part 6 of the MUTCD (g)(2). A citation written today names 1926.200(g), not 1926.202.

29 CFR 1926.202 (removed July 15, 2019) at a glance

Status
Removed July 15, 2019 (SIP-IV, 84 FR 21416): no longer in the CFR
Where the rule lives now
29 CFR 1926.200(g)(1)–(2), Traffic control signs and devices
The standard
Barricades and other traffic control devices must conform to Part 6 of the MUTCD (incorporated by reference, 1926.6)
Also removed with it
1926.203 (Definitions applicable to Subpart G): the MUTCD supplies the definitions
Pairs with
Signs (1926.200(a)–(f), (h)) and signaling/flaggers (1926.201)
Max penalty (2026)
$16,550 per serious violation; $165,514 per willful: cited under 1926.200(g)

What 29 CFR 1926.202 (removed July 15, 2019) required, and where the duty is now

29 CFR 1926.202 was the barricades section of Subpart G (Signs, Signals, and Barricades). Its single sentence required barricades for the protection of employees to conform to Part 6 of the Manual on Uniform Traffic Control Devices (MUTCD). It is still cited in older safety programs, subcontract exhibits and training decks, but it was removed from the Code of Federal Regulations effective July 15, 2019.

The removal came in OSHA's Standards Improvement Project-Phase IV (SIP-IV) final rule, 84 FR 21416 (May 14, 2019). OSHA rewrote 1926.200(g) so that paragraph (g)(1) requires traffic control signs and devices at points of hazard and paragraph (g)(2) requires the design and use of all traffic control devices (signs, signals, markings, barricades and other devices) to conform to Part 6 of the MUTCD. With (g)(2) covering barricades expressly, OSHA deleted 1926.202 as duplicative and deleted 1926.203 (definitions) because the MUTCD defines the same terms. The same rule updated the incorporated MUTCD from the Millennium Edition to the 2009 Edition.

The 2019 rule also changed the incorporated MUTCD edition and clarified the scope; it does not state that all the old and new technical requirements are identical. A barricade violation today is written under 1926.200(g)(1) or (g)(2). The current texts are 1926.200(g) and 1926.6(n); the change comes from the SIP-IV final rule of May 14, 2019. Cones and barriers conforming to the MUTCD do not by themselves guarantee the restraint of a vehicle.

The regulatory text

“The design and use of all traffic control devices, including signs, signals, markings, barricades, and other devices, for protection of construction workers shall conform to Part 6 of the MUTCD (incorporated by reference, see § 1926.6).”
29 CFR 1926.200(g)(2)

Key facts about 29 CFR 1926.202 (removed July 15, 2019)

  • 1926.202 was removed from the CFR effective July 15, 2019 (SIP-IV final rule, 84 FR 21416, May 14, 2019).
  • Its requirement, barricades conform to Part 6 of the MUTCD, now sits in 1926.200(g)(2).
  • 1926.200(g)(1) requires traffic control signs and devices at points of hazard in construction areas.
  • 1926.203 (definitions for Subpart G) was removed in the same rule; the MUTCD supplies the definitions.
  • The MUTCD is incorporated by reference through 1926.6 (2009 Edition since SIP-IV).
  • The MUTCD edition incorporated by OSHA is the 2009 edition with revisions 1 and 2 of May 2012 (1926.6(n)). Citations are written under 1926.200(g), not 1926.202.
  • Signs (1926.200) and flaggers (1926.201) remain the other two legs of Subpart G.

Former requirements of 29 CFR 1926.202 (removed July 15, 2019)

#What the section requires or covers
1Cite 1926.200(g), not 1926.202, for barricade violations
2Barricades and other traffic control devices conform to Part 6 of the MUTCD (1926.200(g)(2))
3Points of hazard posted with traffic control signs and protected by devices (1926.200(g)(1))

Removed section, current paragraph

SIP-IV deleted 1926.202 because 1926.200(g)(2) covers barricades and every other traffic control device. The removal is not a relaxation, and the rule did not state that every old technical prescription is identical to the new one: the MUTCD edition changed and the scope was clarified. Programs and subcontract exhibits that cite 1926.202 are updated for their operational requirements; historical citations and contracts may be kept with their date when needed. A traffic control device that separates traffic from a work area is not the same as protection against intrusion or fall; chapter 6F of the MUTCD has its sections by type of device.

What OSHA inspectors look for

A compliance officer looks at the same thing the old section covered (whether the traffic control devices protecting workers, barricades included, conform to Part 6 of the MUTCD, in the edition incorporated by 1926.6: the 2009 edition with revisions 1 and 2 of May 2012) but the citation is written under 1926.200(g)(1) or (g)(2). A safety plan, JHA or subcontract that cites 1926.202 refers to a section that has not existed since July 2019; the devices and the layout are what 1926.200(g) governs.

Example: how a violation is cited

Hypothetical case: a road-construction crew uses cones and improvised barriers that do not conform to the MUTCD to protect a work zone. 1926.200(g)(2) has the design and use of traffic control devices, including barricades, conform to Part 6 of the MUTCD. The company's written program still cites "1926.202", a section removed in 2019. A serious violation carries a penalty of up to $16,550.

Illustrative example, not a specific OSHA case.

Updating documents that still cite 29 CFR 1926.202 (removed July 15, 2019)

  • Update the operational requirements of programs, JHAs and subcontract exhibits to 1926.200(g); keep historical citations with their date where needed.
  • Use traffic control devices that conform to Part 6 of the MUTCD (2009 edition with revisions 1 and 2 of May 2012).
  • Post legible traffic control signs and protect points of hazard with traffic control devices (1926.200(g)(1)).
  • Select the device type from the applicable chapter 6F section for the situation.
  • Coordinate barricades with signs (1926.200) and flaggers (1926.201).

Free compliance tools for 29 CFR 1926.202 (removed July 15, 2019)

Frequently asked questions about 29 CFR 1926.202 (removed July 15, 2019)

Is 29 CFR 1926.202 still in effect?

No. OSHA removed 1926.202 (Barricades) and 1926.203 (Definitions) in the Standards Improvement Project-Phase IV final rule, 84 FR 21416 (May 14, 2019), effective July 15, 2019. The barricade requirement was not dropped: it was folded into the revised 1926.200(g), which requires the design and use of all traffic control devices, including barricades, to conform to Part 6 of the MUTCD.

What does OSHA cite for a non-conforming barricade today?

1926.200(g)(2): the design and use of all traffic control devices, including signs, signals, markings, barricades and other devices, for protection of construction workers shall conform to Part 6 of the MUTCD. Where the problem is a point of hazard with no signs or devices at all, 1926.200(g)(1) applies. Inspectors and OSHA's citation data use these paragraphs, not 1926.202.

Can I use cones or tape instead of barricades?

Only if they conform to the MUTCD for the situation. 1926.200(g)(2) requires the traffic control devices protecting workers to conform to Part 6 of the MUTCD, which specifies which channelizing devices are appropriate and how they must be designed, placed and made retroreflective. An improvised assortment of cones or tape that does not meet the MUTCD, or that fails to separate workers from the hazard, is not compliant.

My safety program still cites 1926.202: do I have to change it?

A program is not correct on the substance simply because it cites 1926.202; the devices and the layout are examined. The citation points to a section that has not existed since July 15, 2019: operational requirements are updated to 1926.200(g) (and 1926.203 definitions to the MUTCD), and historical citations may be kept with their date. OSHA's SIP-IV rule (84 FR 21416) is the primary source for the change.

Regulatory history of 29 CFR 1926.202 (removed July 15, 2019)

The final rule of September 12, 2002 (effective December 11, 2002) simplified the MUTCD reference; the editions then incorporated were the 1988 edition revision 3 or the Millennium edition, since replaced. In the Standards Improvement Project-Phase IV final rule (84 FR 21416, May 14, 2019; effective July 15, 2019), OSHA revised 1926.200(g) to cover the design and use of all traffic control devices, updated the incorporated MUTCD to the 2009 edition with revisions 1 and 2 of May 2012, and removed 1926.202 and 1926.203.

Related glossary terms

Key terms that appear in 29 CFR 1926.202 (removed July 15, 2019), each with a full plain-English explainer.

Get the Binder in Order Before the Inspector Arrives. Are You Ready?

OSHA inspections come unannounced, apart from the few exceptions listed in 29 CFR 1903.6. Get the binder in order before the opening conference, not during it.

Serious Violation

$16,550

per violation (max)

HazComFast Pro

$199/mo

10 jobsites, unlimited chemicals, unlimited workers

New sign-ups are paused. The free tools below need no account, and customers can log in as usual.

Your account keeps working as usual. Cancel anytime.