29 CFR 1926.150

29 CFR 1926.150 requires each employer to develop a fire protection program followed throughout all phases of construction and demolition work, and to provide firefighting equipment, fire extinguishers and a water supply, as specified, without delay as fire hazards appear.

29 CFR 1926.150 at a glance

What it requires
A fire protection program throughout the job, with firefighting equipment provided as hazards arise
Who it covers
Construction and demolition employers
Program rule
Develop and follow a fire protection program for all phases of the work (1926.150(a)(1))
Key duty
Provide, distribute, and maintain firefighting equipment; supply water where required
Max penalty (2026)
$16,550 per serious violation; $165,514 per willful
Common confusion
Water supply, temporary equipment, emergency action plan and the fire protection program are not one interchangeable document

What 29 CFR 1926.150 requires (plain English)

29 CFR 1926.150 sets the fire protection requirements for construction and demolition. It has the employer develop a fire protection program followed throughout all phases of the work, and to provide firefighting equipment as fire hazards arise, without delay.

The standard sets measurable extinguisher rules. A fire extinguisher rated not less than 2A is needed for each 3,000 square feet of protected building area or major fraction thereof, with travel distance from any point to the nearest extinguisher not over 100 feet; at least one 2A extinguisher on each floor, and in a multistory building one adjacent to a stairway; a 10B extinguisher within 50 feet of wherever more than 5 gallons of flammable or combustible liquids or 5 pounds of flammable gas are being used (not integral vehicle fuel tanks); and listed or approved extinguishers, periodically inspected and maintained to NFPA 10A, protected from freezing (1926.150(c)(1)). A 55-gallon open drum of water with two fire pails, or a garden-type hose line of 1/2 inch, up to 100 feet, discharging at least 5 gallons per minute with a 30-foot stream, mounted on racks or reels so one stream reaches all points, may substitute for a 2A extinguisher, and 100 feet or less of 1 1/2 inch hose with a nozzle of 25 gallons per minute or more may substitute where it reaches all points ((c)(1)(ii)-(iii), (c)(2)(i)). A temporary or permanent water supply of sufficient volume, duration and pressure must be made available as soon as combustible materials accumulate ((b)(1)). Standpipes are addressed in (d)(2): in structures in which standpipes are required, or where they exist in structures being altered, they are brought up as soon as applicable laws permit and maintained ready for use as construction progresses; whether a given building needs one is a question of the applicable laws, not simply of the number of stories. An alarm system must be established so employees on the site and the local fire department can be alerted, with the alarm code and reporting instructions conspicuously posted at phones and employee entrances ((e)(1)-(2)). As fire hazards occur, there is no delay in providing the necessary equipment ((a)(1)). Access to all available firefighting equipment is maintained at all times, it is conspicuously located, periodically inspected and maintained in operating condition, and defective equipment is immediately replaced ((a)(2)-(4)). As warranted by the project, the employer provides a trained and equipped firefighting organization (fire brigade) to assure adequate protection to life ((a)(5)); this does not make every employee a firefighter. Where underground water mains are to be provided, they are installed, completed and made available as soon as practicable ((b)(2)). Carbon tetrachloride and other toxic vaporizing liquid fire extinguishers are prohibited ((c)(1)(vii)). If the facility includes automatic sprinkler protection, the installation closely follows the construction and is placed in service as soon as applicable laws permit following completion of each story; during demolition or alterations, existing automatic sprinkler installations are retained in service as long as reasonable, sprinkler control valves are operated only by properly authorized persons and are checked daily at close of work ((d)(1)). Fire walls and exit stairways required for the completed buildings are given construction priority, and fire doors with automatic closing devices are hung as soon as practicable ((f)(1)). The employer's emergency action plan and the fire protection program of 1926.150 are different documents; the 1910.39 requirements are not imported.

1926.150 is in Subpart F (fire protection and prevention); the flammable-liquid (1926.152), LP-gas, 1926.151 (fire prevention) and 1926.153 and 1926.352 provisions have their own requirements.

The regulatory text

“The employer shall be responsible for the development of a fire protection program to be followed throughout all phases of the construction and demolition work, and he shall provide for the firefighting equipment as specified in this subpart. As fire hazards occur, there shall be no delay in providing the necessary equipment.”
29 CFR 1926.150(a)(1)

Key facts about 29 CFR 1926.150

  • The employer must develop a fire protection program followed throughout all phases of the work (1926.150(a)(1)).
  • Firefighting equipment must be provided without delay as fire hazards occur.
  • Fire extinguishers must be rated at least 2A for each 3,000 square feet or major fraction, within 100 feet of travel, with at least one on each floor and by a multistory stairway, and a 10B within 50 feet of flammable liquid or gas use above the thresholds (1926.150(c)(1)); the Table F-1 selection is a guide.
  • A temporary or permanent water supply of sufficient volume, duration and pressure for the firefighting equipment must be available as soon as combustible materials accumulate (1926.150(b)(1)), whatever the size of the project.
  • Where standpipes are required, or exist in structures being altered, they are brought up as soon as applicable laws permit and kept ready for use as construction progresses (1926.150(d)(2)); whether a structure requires one depends on the applicable laws.
  • An alarm system must alert employees and the local fire department, with the alarm code and reporting instructions posted at phones and employee entrances (1926.150(e)).
  • Listed or approved extinguishers are used, and the water-drum and hose substitutions apply on their conditions (1926.150(c)(1)-(2)).
  • Access to all available firefighting equipment is maintained at all times; it is conspicuously located and periodically inspected and maintained in operating condition (1926.150(a)(2)-(4)).
  • As warranted by the project, the employer provides a trained and equipped firefighting organization (1926.150(a)(5)).

Scope: who 29 CFR 1926.150 applies to

Regulatory framework
Construction (29 CFR 1926)
Citation reference
29 CFR 1926.150
Enforcement status
In force and enforced
Jurisdiction
Federal OSHA (29 State-Plan jurisdictions may be stricter)

State-Plan states (e.g. California, Washington, Michigan) operate OSHA-approved programs that must be at least as effective as federal OSHA and frequently impose higher penalties or additional requirements.

Key requirements of 29 CFR 1926.150

#What the section requires or covers
1Develop a fire protection program to be followed throughout all phases of the construction and demolition work, with the firefighting equipment the subpart specifies and no delay as fire hazards occur (1926.150(a)(1))
2Provide a water supply of sufficient volume, duration and pressure to operate the firefighting equipment as soon as combustible materials accumulate (1926.150(b)(1))
3Provide a fire extinguisher rated at least 2A for each 3,000 square feet of protected building area, or major fraction, with travel distance to the nearest extinguisher not exceeding 100 feet (1926.150(c)(1)(i)); provide one rated at least 10B within 50 feet of where more than 5 gallons of flammable or combustible liquids or 5 pounds of flammable gas are used (1926.150(c)(1)(vi))
4In structures where standpipes are required, or exist in structures being altered, bring them up as construction progresses and keep them ready for use (1926.150(d)(2))
5Keep access to firefighting equipment, inspect it periodically and replace defective equipment immediately (1926.150(a)(2)-(4)); establish an alarm system so that employees and the fire department can be alerted (1926.150(e))

Summarized from the text of 29 CFR 1926.150.

Common Fire Protection (Construction) violations

Deficiencies OSHA cites under 29 CFR 1926.150 include the ones below, in no particular order. Each serious item carries up to $16,550 (2026).

  • No fire protection program for the project (1926.150(a)(1)).
  • Fire extinguisher missing, below 2A for the area (3,000 square feet or major fraction), beyond 100 feet of travel, not on each floor or by the stairway of a multistory building, or no 10B within 50 feet of flammable liquid or gas use above the thresholds (1926.150(c)(1)).
  • Extinguishers blocked, unmaintained, or discharged (1926.150(c)).
  • No water supply of sufficient volume, duration and pressure once combustible materials have accumulated (1926.150(b)(1)).
  • Standpipes that are required, or that exist in a structure being altered, not brought up as soon as applicable laws permit and kept ready for use (1926.150(d)(2)); no alarm system alerting employees and the local fire department, or alarm code and instructions not posted ((e)).

Water supply, equipment and the program

1926.150(a)(1) has the employer responsible for the development of a fire protection program to be followed throughout all phases of the construction and demolition work, and the firefighting equipment as specified in the subpart, with no delay in providing the necessary equipment as fire hazards occur. 1926.150(b)(1) has a temporary or permanent water supply, of sufficient volume, duration and pressure, made available as soon as combustible materials accumulate. The paragraph on standpipes (d)(2) applies to structures in which they are required or where they exist in structures being altered; the applicable law decides the height, not 1926.150. The water supply, the temporary equipment, the emergency action plan and the fire protection program are not one interchangeable document.

What OSHA inspectors look for

A compliance officer checks that a fire protection program exists and is followed, that fire extinguishers of the right type and rating are provided, accessible, and maintained across the site, and that a water supply and standpipes are available where required. Access to all available firefighting equipment is maintained at all times, and it is conspicuously located, periodically inspected and maintained in operating condition (1926.150(a)(2)-(4)).

Example: how a violation is cited

Hypothetical case: a multi-story project has no fire protection program and extinguishers that do not meet the numbers of 1926.150(c)(1). 1926.150(a)(1) has the employer responsible for the development of a fire protection program followed throughout all phases of the work. A serious violation carries a penalty of up to $16,550.

Illustrative example, not a specific OSHA case.

Fire Protection (Construction) compliance checklist

Each item is a requirement of 29 CFR 1926.150 that OSHA may verify during an inspection.

  • Develop and apply a fire protection program followed throughout all phases of construction and demolition work (1926.150(a)(1)). Putting it in writing is good practice, but 1926.150(a)(1) does not itself require a written document.
  • Distribute extinguishers by the numbers: 2A per 3,000 square feet or major fraction, 100 feet maximum travel, one per floor and by the stairway, 10B within 50 feet of more than 5 gallons of flammable or combustible liquid or 5 pounds of flammable gas in use.
  • Keep extinguishers accessible, maintained, and inspected, and replace discharged units.
  • Provide a temporary or permanent firefighting water supply of sufficient volume, duration and pressure as soon as combustible materials accumulate (1926.150(b)(1)).
  • Where standpipes are required or exist in a structure being altered, bring them up as soon as applicable laws permit and keep them ready for use as construction proceeds; establish an alarm system for employees and the local fire department and post the alarm code and reporting instructions (1926.150(d)(2), (e)).
  • Apply the fire prevention (1926.151), flammable liquids (1926.152), LP-gas (1926.153) and hot work (1926.352) provisions where they apply.

2026 penalties for 29 CFR 1926.150

Maximums set by 29 CFR 1903.15(d). 2026 maximums unchanged from 2025 (no CPI adjustment; OMB M-26-11), so not an increase; the serious and repeat policy minimums were revised with FOM chapter 6 (OSHA memo of May 21, 2026). The 2025 OSHA penalty levels remain in effect for 2026; OSHA made no inflation adjustment for 2026. 29 CFR 1903.15 identifies January 15, 2025 as the effective reference for these amounts, while OSHA's public penalties page currently references penalties assessed after Jan. 15, 2026.

Violation typeMinimumMaximumWhen it applies
Serious$1,085$16,550Death or serious physical harm could result, and the employer knew or could have known (29 U.S.C. 666(k)).
Other-Than-Serious$0$16,550Relates to safety/health but unlikely to cause death or serious harm.
Willful$11,823$165,514Intentional, knowing, or voluntary disregard of the requirement.
Repeated$4,256$165,514A substantially similar violation cited within the last 5 years.
Failure to AbateNone$16,550/dayup to $16,550 per day; the total is normally capped at 30 times the daily amount (FOM Ch.6)

Serious violations reach $16,550 and willful or repeat violations $165,514.

Maximums and the willful minimum are set by 29 CFR 1903.15(d); the serious and repeated minimums are OSHA policy floors from its annual penalty adjustment memo. OSHA applies gravity-based and size, good-faith and history reductions (FOM CPL 02-00-164 Ch.6). Estimates only, not legal advice.

The business case for Fire Protection (Construction) compliance

1926.150(a)(1) has the employer responsible for the development of a fire protection program to be followed throughout all phases of the construction and demolition work, with the firefighting equipment as specified in the subpart and no delay in providing the necessary equipment as fire hazards occur.

State plans and their penalty rules

States listed by the volume of their federal construction citations, not by this standard. Penalties and enforcement vary by state. State-Plan states may impose higher penalties and additional requirements beyond federal 29 CFR 1926.150.

State pages for 29 CFR 1926.150

Frequently asked questions about 29 CFR 1926.150

What does 1926.150 require for construction fire protection?

Under 1926.150(a)(1), each employer must develop a fire protection program followed throughout all phases of the construction and demolition work and provide firefighting equipment as specified, with no delay as fire hazards occur. In practice that means fire extinguishers rated and spaced as paragraph (c) sets, kept accessible and maintained, a firefighting water supply once combustibles accumulate, standpipes where they are required or exist, and an alarm system. The paragraph does not itself require the program to be written; a written program is good practice.

When does construction fire protection have to be in place?

Throughout all phases of the work. 1926.150(a)(1) requires the fire protection program to be followed from the start and states there shall be 'no delay in providing the necessary equipment' as fire hazards occur, and the water supply is available as soon as combustible materials accumulate ((b)(1)).

How many fire extinguishers does a construction site need?

At least a 2A-rated extinguisher for each 3,000 square feet of protected building area or major fraction, with travel distance not over 100 feet, at least one on each floor and by the stairway in a multistory building, and a 10B within 50 feet of where more than 5 gallons of flammable or combustible liquids or 5 pounds of flammable gas are used (1926.150(c)(1)). They must be conspicuously located, accessible, maintained, and inspected.

Are standpipes required during construction?

Where standpipes are required, or where they exist in structures being altered. Under 1926.150(d)(2), in all structures in which standpipes are required, or where standpipes exist in structures being altered, they must be brought up as soon as applicable laws permit and be maintained as construction progresses so they are always ready for fire protection use. Whether a standpipe is required depends on the applicable laws, not simply on the number of stories. Separately, a water supply of sufficient volume, duration and pressure must be available as soon as combustible materials accumulate ((b)(1)).

Regulatory history of 29 CFR 1926.150

1926.150 is in Subpart F (Fire Protection and Prevention).

Related glossary terms

Key terms that appear in 29 CFR 1926.150, each with a full plain-English explainer.

Get the Binder in Order Before the Inspector Arrives. Are You Ready?

OSHA inspections come unannounced, apart from the few exceptions listed in 29 CFR 1903.6. Get the binder in order before the opening conference, not during it.

Serious Violation

$16,550

per violation (max)

HazComFast Pro

$199/mo

10 jobsites, unlimited chemicals, unlimited workers

New sign-ups are paused. The free tools below need no account, and customers can log in as usual.

Your account keeps working as usual. Cancel anytime.