Skip to content

Approaching: Feb 1, 2027 — 300A Posting Begins. Get ready →

Construction · CAS Database

Actinolite Asbestos

Actinolite Asbestos (CAS 77536-66-4): Regulated asbestos mineral. What OSHA's HazCom rules ask of it on a job site, and where its Safety Data Sheet comes from: your supplier.

CAS Registry Number CAS 77536-66-4

Overview

Regulated asbestos mineral

OSHA Exposure Limits

OSHA permissible exposure limit (PEL) and secondary limit for Actinolite Asbestos on a US construction site. Where a substance-specific 1926 standard applies, its codified limit is shown; otherwise the figure comes from Table 1 to 29 CFR 1926.55, the construction air-contaminants table. Where Table 1 gives no figure, either the substance has its own standard (the row says "see 1926.xxxx" and this page names that standard) or Table 1 sets no limit for it. In both cases Section 8 of the Safety Data Sheet lists the limits other bodies recommend and the supplier's controls.

LimitValueBasis / citation
OSHA PEL (0.1 f/cc 8-hr TWA + 1.0 f/cc 30-min excursion limit — 29 CFR 1926.1101(c))0.1 f/cc29 CFR 1926.1101
excursion limit (30-min)1 f/ccShort-term concentration that must not be exceeded
Averaging period0.1 f/cc 8-hr TWA + 1.0 f/cc 30-min excursion limit — 29 CFR 1926.1101(c)The ACGIH TLV and NIOSH REL are recommendations; some are lower than the PEL

Many OSHA PELs date to 1971 and may be less protective than current ACGIH/NIOSH values; always check Section 8 of the manufacturer SDS for the limits it lists, which can be lower than the PEL, and for its control guidance. Not legal advice.

Which OSHA rules apply to this substance

Actinolite asbestos is named in the definition of "asbestos" at 29 CFR 1926.1101(b), so the construction asbestos standard governs it in full, and a generic dust rule does not.

LimitFormSource
0.1 fiber per cubic centimetre8-hour TWA29 CFR 1926.1101(c)(1)
1.0 fiber per cubic centimetreexcursion limitmeasured over 30 minutes: a short burst can breach this while the 8-hour average (29 CFR 1926.1101(c)(1)) still looks compliant29 CFR 1926.1101(c)(2)

29 CFR 1926.1101far more than a number: classification of the work into Class I–IV, a competent person, negative-exposure assessments, regulated areas, specific engineering controls and work practices, medical surveillance, and notification before demolition or renovation.

The definition of asbestos at 29 CFR 1926.1101(b) lists actinolite asbestos, and "any of these minerals that has been chemically treated and/or altered".

Identify the work class before anything else: Class I removal of thermal system insulation is a different regime from Class IV housekeeping. Note the one carve-out in the standard's own scope: 1926.1101 does not apply to asbestos-containing asphalt roof coatings, cements and mastics.

OSHA & HazCom Compliance Requirements

For construction work, Hazard Communication is governed by 29 CFR 1926.59 (adopts 29 CFR 1910.1200). Where a product your crews use contains Actinolite Asbestos and is a hazardous chemical under the standard (its supplier's label and SDS say so), the employer must:

  • •Maintain an accessible SDS for Actinolite Asbestos (readily accessible during each work shift, 29 CFR 1910.1200(g)(8))
  • •Keep the supplier's label on shipped containers (29 CFR 1910.1200(f)(1)) and mark workplace containers with the shipped-label elements or the product identifier and hazard information (29 CFR 1910.1200(f)(6)); a portable container for immediate use by the person who filled it needs none (1910.1200(f)(8))
  • •Include it in the workplace chemical inventory
  • •Train employees on hazards before initial assignment
  • •Retain employee exposure and medical records per 29 CFR 1910.1020: exposure records for at least 30 years, medical records for the duration of employment plus 30 years. An SDS itself may be discarded if a record of the chemical's identity, where it was used and when is kept for 30 years

Substance-specific standard: Asbestos (actinolite)

In addition to HazCom, this chemical is regulated under 29 CFR 1926.1101. Regulated asbestos. Construction work with asbestos-containing material is governed by 29 CFR 1926.1101. PEL 0.1 f/cc (8-hr TWA); excursion limit 1 f/cc over 30 minutes.

Asbestos has its own section in Subpart Z of 29 CFR 1926 (1926.1101). The limits and what each standard requires, side by side: OSHA substance-specific standards.

HazCom (1910.1200 / construction 1926.59) covers hazard classification, labels, SDSs, the written program (with its chemical list and the rules for non-routine tasks and multi-employer sites) and training. It does not impose chemical storage segregation. Flammable & combustible liquid storage for construction is 29 CFR 1926.152; segregation of incompatibles is planned from SDS Sections 7 and 10. Exemptions apply, such as a consumer product used the way a consumer would use it (1910.1200(b)(6)(ix)). Not legal advice; state-plan states may have stricter rules.

Handling & Secondary-Container Labeling

When you transfer Actinolite Asbestos into a workplace (secondary) container, OSHA gives two compliant options under 29 CFR 1910.1200(f)(6):

  • •(f)(6)(i): full GHS label elements (as on the shipped container)
  • •(f)(6)(ii): product identifier + words/pictures/symbols (or combination) that provide AT LEAST general information on the hazards and, with the other information immediately available under the HazCom program, the specific hazards

There is no volume/size cutoff for secondary containers: the ≤100 ml / ≤3 ml accommodations (29 CFR 1910.1200(f)(12) (added by the HCS 2024 final rule)) apply only to the manufacturer's shipped container. A portable container filled for the immediate use of the worker who fills it needs no label (29 CFR 1910.1200(f)(8)).

GHS Hazard Classification under OSHA HCS

OSHA's Hazard Communication Standard adopts the GHS (primarily GHS Revision 7 (HCS 2024)). It uses 8 hazard pictograms (Appendix C, Figure C.1); a label carries only the ones its classification calls for. The Environment pictogram (GHS09) is not required by OSHA. Not in App C; outside OSHA jurisdiction; voluntary.

The eight HCS pictograms:

FlameFlame Over CircleExclamation MarkExploding BombCorrosionGas CylinderHealth HazardSkull and Crossbones

For flammable liquids, OSHA classifies by flash point and boiling point (App B.6.1 / 1910.106(a)):

  • •Category 1: FP < 73.4°F AND BP <= 95°F
  • •Category 2: FP < 73.4°F AND BP > 95°F
  • •Category 3: FP >= 73.4°F AND <= 140°F
  • •Category 4: FP > 140°F AND <= 199.4°F

The GHS classification of a product that contains Actinolite Asbestos comes from Section 2 of that product's Safety Data Sheet: the pictograms and categories on your labels follow that section.

HCS 2024 Update Deadlines

Under the federal Hazard Communication Standard 2024 update (aligned primarily GHS Revision 7):

  • •May 19, 2026: manufacturers, importers, and distributors of Actinolite Asbestos sold as a substance update its labels & SDSs (1910.1200(j)(2)(i))
  • •November 20, 2026: for the substance, employers, as necessary, update alternative workplace labels, the written program & training for newly identified hazards (1910.1200(j)(2)(ii))
  • •For a mixture that contains Actinolite Asbestos: November 19, 2027 for manufacturers, importers and distributors, and May 19, 2028 for employers, as necessary (1910.1200(j)(3))

During the interim, parties may comply with the 2012 HCS, the 2024 HCS, or both. These are the federal OSHA dates; State Plans adopt the update on their own schedules, so check your state.

Quick Actions

Put Actinolite Asbestos on your written inventory, print the workplace label your containers need, and keep your supplier’s sheet reachable on the jobsite.

The safety data sheet for your product comes from the supplier who sold it to you. No public registry can provide it. For the underlying chemistry, the public record is on PubChem.

Where this fits in your HazCom program

  • SDS management: collecting the sheet, keeping it current, and making it readable during each work shift.
  • GHS labels & workplace labeling: what has to appear on the shipped container, and what a secondary container needs instead.

Frequently Asked Questions

What is Actinolite Asbestos (CAS 77536-66-4)?

Regulated asbestos mineral

What are the OSHA HazCom requirements for Actinolite Asbestos on a construction site?

For construction work, Hazard Communication is governed by 29 CFR 1926.59 (adopts 29 CFR 1910.1200). Where a product you use containing Actinolite Asbestos is a hazardous chemical under the standard (its supplier's label and SDS say so), you must keep its Safety Data Sheet accessible, keep the supplier's label on shipped containers and label workplace containers under (f)(6), list it in the written program's chemical inventory, and train workers on its hazards at initial assignment. Exemptions apply, such as a consumer product used the way a consumer would use it (1910.1200(b)(6)(ix)).

Is there a substance-specific OSHA standard for Actinolite Asbestos?

Yes. In addition to HazCom, Asbestos (actinolite) is regulated under 29 CFR 1926.1101. The 8-hour TWA permissible exposure limit (PEL) is 0.1 f/cc, with an excursion limit (30-min) of 1 f/cc. Regulated asbestos. Construction work with asbestos-containing material is governed by 29 CFR 1926.1101. PEL 0.1 f/cc (8-hr TWA); excursion limit 1 f/cc over 30 minutes.

What is the OSHA permissible exposure limit (PEL) for Actinolite Asbestos?

OSHA's 8-hour time-weighted-average PEL for Asbestos (actinolite) is 0.1 f/cc, with an excursion limit (30-min) of 1 f/cc (29 CFR 1926.1101). Section 8 of the manufacturer Safety Data Sheet lists the exposure limits the supplier reports and its control advice; the limit OSHA enforces is the one in its standard, and a State Plan may set its own.

When does the updated HCS 2024 labeling apply to Actinolite Asbestos?

Under the federal Hazard Communication Standard 2024 update (aligned primarily GHS Revision 7), manufacturers, importers and distributors must comply by May 19, 2026 when Actinolite Asbestos is sold as a substance, and by November 19, 2027 for mixtures that contain it. Employers must, as necessary, update alternative workplace labels, the written program and training for newly identified hazards by November 20, 2026 for substances and May 19, 2028 for mixtures (29 CFR 1910.1200(j)). During the interim, parties may comply with the 2012 HCS, the 2024 HCS, or both. State Plans adopt the update on their own schedules, so check your state's dates.

How do I label a secondary (workplace) container of Actinolite Asbestos?

Under 29 CFR 1910.1200(f)(6) you have two options: (i) the label elements of (f)(1)(i) through (v): product identifier, signal word, hazard statements, pictograms and precautionary statements, with no supplier name or address needed, or (ii) the product identifier plus words, pictures, symbols, or a combination that provide at least general hazard information and that, with the other information immediately available to workers under the HazCom program, give the specific hazards. There is no volume/size cutoff for secondary containers. A portable container filled from a labeled container, kept under the control of the worker who fills it and used only by that worker within the same shift, does not require a label (29 CFR 1910.1200(f)(8)).

How long must SDS and exposure records for Actinolite Asbestos be kept?

Under 29 CFR 1910.1020, 30-year retention applies to employee exposure and medical records (medical records: duration of employment plus 30 years), not to SDSs generically. Where an SDS is not retained, a record of the chemical's identity, where it was used, and when must be kept for at least 30 years.

Where can I find the SDS for Actinolite Asbestos?

Under 29 CFR 1910.1200(g)(6) and (g)(7), the manufacturer or importer of Actinolite Asbestos must ensure that distributors and employers receive its Safety Data Sheet with the initial shipment and with the first shipment after the sheet is updated, and a distributor passes it on in its commercial shipments the same way. Retail and wholesale distributors that sell to employers over the counter or to commercial accounts have their own duties in (g)(7)(iii) to (vii), such as providing the sheet on request. HazComFast keeps the sheets you collect in one inventory per jobsite, searchable by product, manufacturer or CAS number, and your jobsite's SDS load onto the phone on their own.

Regulatory data on this page comes from 29 CFR 1926.59 / 1910.1200 and substance-specific 1926 standards, last verified October 19, 2026 against eCFR, OSHA.gov, and the Federal Register. Physical-property data comes from PubChem; the source of a figure is in parentheses after it where one is given (NIOSH Pocket Guide, ICSC, or the dataset PubChem cites). Confirm it against the manufacturer Safety Data Sheet. This page is informational and is not legal advice.

Looking for more chemicals?

Browse our database of industrial chemicals with GHS data, safety information, and compliance tools.

Get the Binder in Order Before the Inspector Arrives. Are You Ready?

OSHA inspections come unannounced, apart from the few exceptions listed in 29 CFR 1903.6. Get the binder in order before the opening conference, not during it.

Serious Violation

$16,550

per violation (max)

HazComFast Pro

$199/mo

10 jobsites, unlimited chemicals, unlimited workers

New sign-ups are paused. The free tools below need no account, and customers can log in as usual.

Your account keeps working as usual. Cancel anytime.