29 CFR 1910.147 · Georgia

Lockout/Tagout (LOTO) Requirements in Georgia

Lockout/Tagout (LOTO) in Georgia: 2026 penalties, who enforces 29 CFR 1910.147, the paragraphs cited and free tools.

Verified vs OSHA sources · 2026-10-05

GeorgiaGeneral Industry (29 CFR 1910)Federal OSHA Jurisdiction

In Georgia, a serious violation of 29 CFR 1910.147 (Lockout/Tagout (LOTO)) carries a maximum penalty of $16,550 per violation in 2026, rising to $165,514 for a willful or repeat violation. Lockout/Tagout (LOTO) is enforced for private construction employers by federal OSHA.

29 CFR 1910.147 does not apply to construction work. In Georgia, federal OSHA enforces 29 CFR 1910.147. The federal maximum for a serious violation is $16,550.

$16,550

federal maximum for a serious violation

$165,514

federal maximum for a willful or repeat violation

3.4

fatal work injuries per 100,000 full-time workers, all industries, Georgia, 2024 (BLS)

What federal OSHA is targeting in Georgia

Georgia has no state OSHA plan for private-sector work, so there is no state rule to read. What differs here is which hazards federal OSHA schedules inspections for, as set out in published emphasis directives.

Regional Emphasis Program (REP) for Electrical Hazards

ATL-CPL-04-00-001 · Atlanta Regional Office · effective October 1, 2024

“This instruction applies to all Atlanta Region Federal Offices.”

Electrical hazards are programmed across the Atlanta region's federal offices. It is the directive that reaches hazardous energy control in Florida and Georgia: an electrical inspection examines whether the circuit was actually de-energised and locked, which is a 1910.147 question before it is a Subpart S one.

Read the directive · verified 2026-08-09

Regional Emphasis Program (REP) addressing Sanitation and Clean-Up Operations

ATL-CPL-04-00-003 · Atlanta Regional Office · effective October 1, 2024

“This instruction applies to all Atlanta Region Federal Offices.”

Sanitation and clean-up in food and beverage manufacturing (NAICS 311xxx and 3121xx) is programmed across the region's federal offices. Sanitation is where the two standards meet: crews work with caustic and chlorinated cleaning chemicals that need classification, labeling and training, on machinery that has to be locked out before anyone reaches inside it.

Read the directive · verified 2026-08-09

Every emphasis program, region by region

Lockout/Tagout (LOTO) Cases in Georgia

Bonded Logic Inc.

$423,432

LaFayette, Georgia - machine-roller injury · 2023

A 21-year-old line operator suffered severe head trauma after being caught in a machine's roller in August 2022. OSHA found the employer willfully failed to develop and use lockout/tagout procedures for workers servicing dangerous machinery, and cited two willful, two repeat and 10 serious violations, including repeat machine-guarding and forklift-certification failures. The proposed penalty was $423,432.

U.S. Department of Labor / OSHA news release, March 6, 2023

How Georgia Enforces 29 CFR 1910.147

Georgia has no State Plan, so federal OSHA has jurisdiction. 29 CFR 1910.147 is enforced by U.S. Department of Labor compliance officers using standard federal procedures and the federal penalty maximums.

29 CFR 1910.147 is a general-industry standard and does not govern construction work. “This standard does not cover the following: (A) Construction and agriculture employment”. Branding a construction program “1910.147 compliant” cites the wrong standard. Unlike confined spaces, Part 1926 has no wholesale re-enactment of 1910.147: construction energy-control duties are spread across hazard-specific provisions, so no single construction equivalent is named here. A Georgia contractor auditing against 29 CFR 1910.147 is auditing against the wrong standard. The citation an officer writes on a construction site will name the 1926 provision, not this one.

Help and oversight in Georgia

Free, confidential help: OSHA On-Site Consultation

In Georgia, the program is Georgia On-Site Safety and Health Consultation Program (Georgia Tech, Enterprise Innovation Institute). OSHA describes it as “Primarily for smaller businesses, no-cost, confidential consultations help employers identify and address hazards and establish or improve safety and health programs.” It is separate from OSHA enforcement; the employer commits to correcting serious hazards.

Georgia consultation program · OSHA consultation directory

Who inspects private employers here

Federal OSHA, from the Atlanta East Area Office (Atlanta), the Atlanta West Area Office (Atlanta) and the Savannah Area Office (Savannah).

OSHA offices for Georgia

Read on osha.gov and the state's official statute site, September 26, 2026.

Georgia Penalty Amounts for 29 CFR 1910.147 (2026)

Verified · 2026-10-05
Violation type2026 maximumBasis
Serious$16,550Federal max · 29 CFR 1903.15(d)
Willful$165,514Federal max · 29 CFR 1903.15(d)
Repeat$165,514Federal max · 29 CFR 1903.15(d)
Failure to abate$16,550/dayup to $16,550 per day; total capped at 30x the daily amount (FOM Ch.6)

Georgia applies the federal OSHA maximums. Amounts are ceilings per violation. Federal OSHA reduces the proposed penalty for employer size, good faith and history (FOM CPL 02-00-164 Ch. 6). There was no inflation increase for 2026: the 2025 amounts remain in effect (OMB Memo M-26-11).

Key Lockout/Tagout (LOTO) Requirements 29 CFR 1910.147

  • Develop machine-specific energy control procedures
  • Train authorized, affected, and other employees
  • Use standardized lockout/tagout devices
  • Follow the 6-step LOTO sequence
  • Conduct annual periodic inspections of procedures
  • Coordinate group lockout for multi-employee servicing

Who enforces it in Georgia: Federal OSHA inspects private construction employers; Georgia has no State Plan.

The compliance checklist, the paragraphs OSHA cites nationally and what an inspector checks under 29 CFR 1910.147 are on the 29 CFR 1910.147 page.

What a Lockout/Tagout (LOTO) Violation Looks Like

Each item below breaches a specific paragraph of 29 CFR 1910.147. It is a list of requirements, not a ranking. A serious violation carries up to $16,550.

  • No documented, machine-specific energy control procedures (1910.147(c)(4)).
  • Failure to conduct the required at-least-annual periodic inspection of procedures (1910.147(c)(6)).
  • Authorized/affected employees not trained (or retrained after changes) (1910.147(c)(7)).
  • Stored or residual energy not released or restrained before servicing (1910.147(d)(5)).
  • No verification of de-energization/isolation before work begins (1910.147(d)(6)).

Georgia Safety & Enforcement Profile

26,559

Federal construction citations (national, FY2025)
1,541 of them in Georgia (HazComFast count)

Federal OSHA

Enforces private construction

  • Construction trades inspected most in Georgia, FY2025: Framing Contractors (290), Roofing Contractors (163) and Siding Contractors (99), out of 885 inspections opened (federal OSHA and State Plan combined).
  • Construction fatality rate in Georgia, 2024: 10.2 per 100,000 full-time workers, 14th highest of the 40 states BLS published (all industries: 3.4).

HazComFast count from the Labor Department's OSHA enforcement data: inspections of construction employers (NAICS 23) opened from October 1, 2024 to September 30, 2025, federal OSHA and State Plan combined, grouped by the inspected employer's 2022 NAICS industry. Industry names are the Census Bureau's 2022 NAICS titles. data.dol.gov · BLS fatality rates by state, 2024

Free Lockout/Tagout (LOTO) Compliance Tools

Lockout/Tagout (LOTO) FAQ for Georgia

Which Georgia industries most often face a Lockout/Tagout (LOTO) inspection?

Lockout/Tagout (LOTO) inspections reach general-industry employers in Georgia, not the construction trades. Federal OSHA inspects these employers directly, since Georgia has no state plan covering the private sector. A construction employer is not governed by 29 CFR 1910.147, and the construction-side duties on this subject are not concentrated in a single standard. Check your Part 1926 obligations instead.

How often is Lockout/Tagout (LOTO) cited in Georgia?

29 CFR 1910.147 is enforced against general-industry employers in Georgia, so the construction citation totals published for Georgia (OSHA Frequently Cited Standards, NAICS 23) do not measure it. “This standard does not cover the following: (A) Construction and agriculture employment”. Branding a construction program “1910.147 compliant” cites the wrong standard. Unlike confined spaces, Part 1926 has no wholesale re-enactment of 1910.147: construction energy-control duties are spread across hazard-specific provisions, so no single construction equivalent is named here. A construction employer is not governed by 29 CFR 1910.147, and the construction-side duties on this subject are not concentrated in a single standard. Check your Part 1926 obligations instead.

Does OSHA require a written lockout/tagout program in Georgia?

Yes. 29 CFR 1910.147 requires an energy control program with documented procedures for the equipment serviced, employee training, and a periodic inspection of each procedure at least annually. In Georgia, federal OSHA can cite the missing program or missing machine-specific steps. In the Bonded Logic case, OSHA cited the lockout failures behind a worker's severe head injury as willful.

Who enforces lockout/tagout (1910.147) for Georgia employers?

Federal OSHA. With no State Plan, a compliance officer from OSHA's Atlanta region inspects and cites 1910.147 directly at the federal penalty maximums.

Can I get free OSHA help in Georgia without an inspection?

Yes. OSHA's On-Site Consultation Program in Georgia is Georgia On-Site Safety and Health Consultation Program (Georgia Tech, Enterprise Innovation Institute). OSHA describes it this way: "Primarily for smaller businesses, no-cost, confidential consultations help employers identify and address hazards and establish or improve safety and health programs." Consultations are separate from OSHA enforcement, and the employer commits to correcting serious hazards.

Lockout/Tagout (LOTO) Guides & Resources

Want the complete federal guide for this standard?

Compare this combination against any other state and standard with the enforcement risk lookup.

Sources & verification

Penalty amounts and plan-type data were checked on 2026-10-05 against eCFR, OSHA.gov, and the Federal Register. This page is informational and not legal advice; consult the enforcing agency or counsel for your specific situation.

Get the Binder in Order Before the Inspector Arrives. Are You Ready?

OSHA does not give advance notice of inspections (29 CFR 1903.6). Get the binder in order before the opening conference, not during it.

Serious Violation

$16,550

per violation (max)

HazComFast Pro

$199/mo

10 jobsites, unlimited chemicals, unlimited workers

New sign-ups are paused. The free tools below need no account, and customers can log in as usual.

Your account keeps working as usual. Cancel anytime.