29 CFR 1926.850 sets the preparatory operations of demolition: prior to permitting employees to start demolition operations, an engineering survey is made by a competent person of the structure to determine the condition of the framing, floors, and walls, and possibility of unplanned collapse of any portion of the structure; any adjacent structure where employees may be exposed is similarly checked; the employer has in writing evidence that the survey has been performed ((a)). When employees are required to work within a structure to be demolished which has been damaged by fire, flood, explosion, or other cause, the walls or floor are shored or braced ((b)). Service lines are shut off, capped, or otherwise controlled outside the building line before demolition work is started, with any utility company involved notified in advance ((c)), and it is determined whether hazardous chemicals, gases, explosives, flammable materials, or similarly dangerous substances have been used in any pipes, tanks, or other equipment on the property ((e)).
An engineering survey by a competent person, with evidence in writing that it was performed, and the control of service lines before demolition
Who it covers
Construction employers performing demolition
Survey rule
An engineering survey is made by a competent person prior to permitting employees to start demolition operations; any adjacent structure where employees may be exposed is similarly checked (1926.850(a))
Key duty
Have in writing evidence that the survey was performed (a); shore or brace the walls or floor where employees are required to work within a structure damaged by fire, flood, explosion or other cause (b); control service lines (c); test and purge where dangerous substances are apparent or suspected (e)
Max penalty (2026)
$16,550 per serious violation; $165,514 per willful
Common confusion
Paragraph (a) requires evidence in writing that the survey was performed, not a particular technical report; paragraph (b) concerns shoring or bracing of structures damaged by fire, flood, explosion or other cause, and the utility lines are in (c) and (d); no general registered professional engineer is required by 1926.850
What 29 CFR 1926.850 requires (plain English)
29 CFR 1926.850 governs the preparatory operations that must be completed before any demolition begins. The paragraphs are the survey (a), damaged structures (b), service lines (c)-(d), hazardous substances in pipes, tanks and equipment (e), glass (f), wall openings (g), debris dropped through floor holes (h), other floor openings (i), the sequence of demolition (j) and entrances to multi-story structures (k).
Under (a), prior to permitting employees to start demolition, a competent person makes an engineering survey of the structure to determine the condition of the framing, floors, and walls and the possibility of unplanned collapse of any portion, with adjacent structures where workers may be exposed similarly checked; the employer must have written evidence that the survey was performed. Where employees must work within a structure damaged by fire, flood, explosion or another cause, the walls or floor must be shored or braced ((b)). All electric, gas, water, steam, sewer and other service lines must be shut off, capped or otherwise controlled outside the building line before demolition work is started, with any utility company involved notified in advance ((c)); lines that must stay live are temporarily relocated as necessary and protected ((d)). The employer must also determine whether hazardous chemicals, gases, explosives, flammable materials or similarly dangerous substances have been used in any pipes, tanks or other equipment on the property; when their presence is apparent or suspected, testing and purging must be performed and the hazard eliminated before demolition is started ((e)). Paragraphs (f)-(k) add the removal of glass fragmentation hazards, protection of wall openings to about 42 inches, enclosed debris drop areas, covered floor openings, top-down removal of exterior walls and floors, and sidewalk sheds or canopies at the entrances of multi-story structures.
1926.850 opens Part 1926 Subpart T (demolition). Asbestos and lead have their own standards (1926.1101 and 1926.62). 1926.1101(a) applies to construction work including demolition or salvage of structures where asbestos is present.
The regulatory text
“Prior to permitting employees to start demolition operations, an engineering survey shall be made, by a competent person, of the structure to determine the condition of the framing, floors, and walls, and possibility of unplanned collapse of any portion of the structure.”
29 CFR 1926.850(a)
Key facts about 29 CFR 1926.850
A competent person must make an engineering survey of the structure before demolition begins (1926.850(a)).
The survey determines the condition of framing, floors, and walls and the possibility of unplanned collapse.
Adjacent structures where workers may be exposed must be similarly checked.
The employer must have written evidence that the survey was performed.
Electric, gas, water, steam, sewer and other service lines must be shut off, capped or otherwise controlled outside the building line before demolition work is started, and any utility company involved notified in advance (1926.850(c)); lines kept in service are temporarily relocated as necessary and protected ((d)). Shoring or bracing the walls or floor of a structure damaged by fire, flood, explosion or another cause, when employees must work inside it, is a separate duty in (b).
The employer must determine whether hazardous chemicals, gases, explosives, flammable materials or similarly dangerous substances have been used in any pipes, tanks or other equipment on the property; where their presence is apparent or suspected, testing and purging must be performed and the hazard eliminated before demolition is started (1926.850(e)). The asbestos standard is separate.
Physical protection during preparation: glass fragmentation hazards removed ((f)); wall openings protected to approximately 42 inches ((g)); debris dropped through floor holes without chutes needs a completely enclosed drop area with barricades at least 42 inches high and at least 6 feet back from the projected edge, with warning signs at each level, and removal is not permitted in the lower area until debris handling ceases above ((h)); floor openings not used as drops covered with secured material strong enough for any load ((i)); exterior walls and floors removed from the top down, story by story, except for chute holes, drop holes and similar necessary preparatory work ((j)); entrances to multi-story structures protected by sidewalk sheds or canopies extending at least 8 feet from the face of the building, 2 feet wider than the entrance and able to sustain 150 pounds per square foot ((k)).
It opens Subpart T (demolition); asbestos and lead have their own standards, 1926.1101 and 1926.62.
Scope: who 29 CFR 1926.850 applies to
Regulatory framework
Construction (29 CFR 1926)
Citation reference
29 CFR 1926.850
Enforcement status
In force and enforced
Jurisdiction
Federal OSHA (29 State-Plan jurisdictions may be stricter)
State-Plan states (e.g. California, Washington, Michigan) operate OSHA-approved programs that must be at least as effective as federal OSHA and frequently impose higher penalties or additional requirements.
Key requirements of 29 CFR 1926.850
#
What the section requires or covers
1
Conduct engineering survey before demolition
2
Identify utilities and disconnect/reroute
3
Brace or shore adjacent structures as needed
4
Develop demolition plan
5
Inspect for hazardous materials (asbestos, lead)
Summarized from the text of 29 CFR 1926.850.
Common Demolition Prep violations
Deficiencies OSHA cites under 29 CFR 1926.850 include the ones below, in no particular order. Each serious item carries up to $16,550 (2026).
No engineering survey by a competent person before demolition (1926.850(a)).
No written evidence that the survey was performed (1926.850(a)).
Service lines not shut off, capped or otherwise controlled outside the building line before demolition work started, or the utility company not notified in advance (1926.850(c)); employees working inside a fire-, flood- or explosion-damaged structure whose walls or floor were not shored or braced (1926.850(b)).
Adjacent exposed structures not checked (1926.850(a)).
Pipes, tanks or other equipment not checked for hazardous chemicals, gases, explosives or flammables, or testing and purging not done where such substances were apparent or suspected (1926.850(e)); wall openings, floor openings, debris drop areas or multi-story entrances left unprotected (1926.850(g)-(k)).
What each paragraph covers: survey, damaged structures, utilities and substances
1926.850(a) has an engineering survey made by a competent person prior to permitting employees to start demolition operations, any adjacent structure where employees may be exposed similarly checked, and the employer have in writing evidence that the survey has been performed; the paragraph requires that evidence, not a particular technical report, and it does not require a registered professional engineer. Paragraph (b) concerns the shoring or bracing of the walls or floor when employees are required to work within a structure to be demolished which has been damaged by fire, flood, explosion, or other cause. The service lines are in (c) and (d): they are shut off, capped, or otherwise controlled outside the building line before demolition work is started, with the utility company notified in advance, and if it is necessary to maintain any power, water or other utilities during demolition, the lines are temporarily relocated, as necessary, and protected. Paragraph (e) concerns hazardous chemicals, gases, explosives, flammable materials, or similarly dangerous substances used in pipes, tanks, or other equipment on the property; when their presence is apparent or suspected, testing and purging are performed and the hazard eliminated before demolition is started. A demolition plan is not a text requirement of 1926.850.
What OSHA inspectors look for
A compliance officer asks for the evidence in writing that the engineering survey by a competent person was performed (a), checks that service lines (electric, gas, water, steam, sewer and other) were shut off, capped or otherwise controlled outside the building line and that the utility company involved was notified in advance (c), and that it was determined whether hazardous chemicals, gases, explosives, flammable materials or similarly dangerous substances have been used in pipes, tanks or other equipment, with testing and purging where their presence is apparent or suspected (e). The officer also looks at paragraphs (f) to (k).
Example: how a violation is cited
Hypothetical case: employees start demolition operations of a structure with no engineering survey made by a competent person and no evidence in writing that one was performed. 1926.850(a) has the survey made prior to permitting employees to start demolition operations, and the employer have in writing evidence that it has been performed. A serious violation carries a penalty of up to $16,550.
Illustrative example, not a specific OSHA case.
Demolition Prep compliance checklist
Each item is a requirement of 29 CFR 1926.850 that OSHA may verify during an inspection.
Have a competent person make an engineering survey of the structure before any demolition.
Have the survey determine the condition of the framing, floors, and walls, and the possibility of unplanned collapse of any portion of the structure.
Check adjacent structures where workers could be exposed.
Keep written evidence that the survey was performed.
Shut off, cap or otherwise control all electric, gas, water, steam, sewer and other service lines outside the building line before demolition work starts, notify each utility company in advance, and relocate and protect any line that must stay in service (1926.850(c)-(d)).
Determine whether hazardous chemicals, gases, explosives, flammable materials, or similarly dangerous substances have been used in any pipes, tanks, or other equipment on the property; when their presence is apparent or suspected, perform testing and purging and eliminate the hazard before demolition is started (1926.850(e)); asbestos and lead have their own standards.
Shore or brace the walls or floor of any structure damaged by fire, flood, explosion or another cause before employees work inside it (1926.850(b)).
Protect wall openings to about 42 inches, cover unused floor openings, barricade debris drop areas (42 inches high, 6 feet back), remove exterior walls and floors from the top down, and protect multi-story entrances with canopies (1926.850(g)-(k)).
2026 penalties for 29 CFR 1926.850
Maximums set by 29 CFR 1903.15(d). 2026 maximums unchanged from 2025 (no CPI adjustment; OMB M-26-11), so not an increase; the serious and repeat policy minimums were revised with FOM chapter 6 (OSHA memo of May 21, 2026). The 2025 OSHA penalty levels remain in effect for 2026; OSHA made no inflation adjustment for 2026. 29 CFR 1903.15 identifies January 15, 2025 as the effective reference for these amounts, while OSHA's public penalties page currently references penalties assessed after Jan. 15, 2026.
Violation type
Minimum
Maximum
When it applies
Serious
$1,085
$16,550
Death or serious physical harm could result, and the employer knew or could have known (29 U.S.C. 666(k)).
Other-Than-Serious
$0
$16,550
Relates to safety/health but unlikely to cause death or serious harm.
Willful
$11,823
$165,514
Intentional, knowing, or voluntary disregard of the requirement.
Repeated
$4,256
$165,514
A substantially similar violation cited within the last 5 years.
Failure to Abate
None
$16,550/day
up to $16,550 per day; the total is normally capped at 30 times the daily amount (FOM Ch.6)
Serious violations reach $16,550 and willful or repeat violations $165,514.
Maximums and the willful minimum are set by 29 CFR 1903.15(d); the serious and repeated minimums are OSHA policy floors from its annual penalty adjustment memo. OSHA applies gravity-based and size, good-faith and history reductions (FOM CPL 02-00-164 Ch.6). Estimates only, not legal advice.
The business case for Demolition Prep compliance
1926.850(a) has an engineering survey made by a competent person of the structure, prior to permitting employees to start demolition operations, to determine the condition of the framing, floors, and walls, and possibility of unplanned collapse of any portion of the structure; (c) has service lines shut off, capped, or otherwise controlled outside the building line before demolition work is started; (e) has it determined whether hazardous chemicals, gases, explosives, flammable materials, or similarly dangerous substances have been used in any pipes, tanks, or other equipment on the property.
States listed by the volume of their federal construction citations, not by this standard. Penalties and enforcement vary by state. State-Plan states may impose higher penalties and additional requirements beyond federal 29 CFR 1926.850.
Under 1926.850(a), before employees start demolition a competent person must make an engineering survey of the structure to determine the condition of the framing, floors, and walls and the possibility of unplanned collapse, and adjacent exposed structures must be similarly checked. The employer must have written evidence the survey was performed, and service lines must be shut off, capped or otherwise controlled outside the building line first (1926.850(c)).
Does the demolition engineering survey have to be in writing?
1926.850(a) requires the employer to have in writing evidence that the engineering survey by a competent person was performed; it does not prescribe a particular technical report.
What has to happen to utilities before demolition?
Under 1926.850(c), before demolition work is started all electric, gas, water, steam, sewer, and other service lines must be shut off, capped, or otherwise controlled outside the building line, and any utility company involved must be notified in advance. If maintaining any utility is necessary during demolition, those lines must be temporarily relocated as necessary and protected (1926.850(d)).
How does 1926.850 relate to the asbestos and lead standards?
1926.850(e) covers chemicals, gases, explosives and flammables in pipes, tanks and equipment (testing and purging where their presence is apparent or suspected). Asbestos has its own standard: 1926.1101(a) applies to construction work including demolition or salvage of structures where asbestos is present. Lead is covered by 1926.62. 1926.850 replaces none of them.
Regulatory history of 29 CFR 1926.850
1926.850 opens Part 1926 Subpart T (Demolition).
Related glossary terms
Key terms that appear in 29 CFR 1926.850, each with a full plain-English explainer.
This page is an educational summary, not legal advice.
Get the Binder in Order Before the Inspector Arrives. Are You Ready?
OSHA inspections come unannounced, apart from the few exceptions listed in 29 CFR 1903.6. Get the binder in order before the opening conference, not during it.