Skip to content

Approaching: Feb 1, 2027 — 300A Posting Begins. Get ready →

Three free templates

The OSHA Inspection Kit: Three Separate Templates for the Job Box

A daily pre-task card, a weekly site inspection and a hot work permit with fire watch. Complete each one at the time of the work, print it and keep it with the job file. Free, no email, no account.

A compliance officer asks about the work happening today: who looked at the hazards this morning, who inspected the site, who authorized the torch. These three templates give you a place to record the answers at the time of the work. A completed form records what its author wrote. It does not replace what the inspector sees on site, and one filled in after the fact documents nothing about that day.

Daily Pre-Task / STA Card

What it can document, when completed at the time: What the foreman recorded: the task, the hazards and the controls the crew went over before the work started, signed by the people who were there.

OSHA has no form for it. A completed card records what the foreman says was reviewed that morning, and many general contractors will not let a crew start without one.

Build today's card

Weekly Site Safety Inspection

What it can document, when completed at the time: What the competent person recorded when they walked the site: fall protection, electrical, housekeeping, PPE and the rest, with the date and their name.

29 CFR 1926.20(b)(2) requires “frequent and regular inspections of the job sites, materials, and equipment to be made by competent persons designated by the employers.” It sets no interval and no form. A dated, signed checklist is one way to record that the inspections happen.

Print this week's checklist

Hot Work Permit + Fire Watch

What it can document, when completed at the time: What was recorded before the torch was lit: the area checked, what could burn moved or covered, and the fire watch posted.

On a construction site, 29 CFR 1926.352 sets the fire-prevention duties: move the fire hazards, keep an extinguisher ready, assign a fire watch when normal precautions aren't enough, during the work and for a sufficient period after it. In general industry, 29 CFR 1910.252(a)(2)(iv) asks for the authorization “preferably in the form of a written permit.” A permit records what was done; it does not replace doing it.

Write the permit

Every crew, every day, on the phone

In HazComFast, permits, inspections and near-misses fill in on the phone, even with no signal, and send themselves the moment you're back online. When the inspector asks, the whole record is one export away.

FAQ

OSHA inspection kit questions

Yes. All three documents are built right on the linked tool pages and print as PDFs. No email, no account, nothing to install. None of them is an OSHA-mandated form: 29 CFR 1926.20(b)(2) requires frequent and regular inspections by competent persons, and 1926.352 sets the hot work fire-prevention duties.

Not as a named form. The construction standard requires a safety program with frequent and regular inspections by a competent person (29 CFR 1926.20(b)). A signed pre-task card records that the crew went over the hazards, as the person who completed it wrote it, and many general contractors require one every morning.

29 CFR 1926.352 does not name a permit. It sets the duties: move or protect the fire hazards, keep fire extinguishing equipment ready, and assign a fire watch when normal precautions are not enough. A permit is a simple way to record each duty, and in general industry 1910.252(a)(2)(iv) asks for the authorization preferably in writing.

OSHA says “frequent and regular” (29 CFR 1926.20(b)(2)) and sets no interval. The right frequency depends on the work, the hazards and what changes on the site. The weekly checklist here is a printable aid, not a determination of how often your site must be inspected. Some work needs checks before each shift or after an event, as specific standards require, for example the excavation inspection of 1926.651(k)(1) and the scaffold inspection before each work shift in 1926.451(f)(3), and a State Plan may add its own rules.

No. It is three separate free tools, and each prints its own PDF. The page does not combine them, tie them to a project or time-stamp them together. A completed form records what the person who filled it in wrote: it does not verify the work, the author's qualification or the time of the checks. Complete each one at the time of the work and keep them with the job file; one filled in afterward records the later date, not the day of the work.